Rox Resources Secures Native Title Agreement With Badimia Barna at Youanmi
Rox Resources (ASX: RXL) has announced a string of meaningful operational milestones at its 100%-owned Youanmi Gold Mine in Western Australia, marking what the company describes as a pivotal moment in its pathway to production. The ROX Resources Youanmi Gold Mine main pit dewatered and underground development update confirms the completion of Main Pit dewatering, a record month of underground development at United North, confirmed high-grade mineralisation at the first ore lode, and rapidly advancing surface infrastructure — all pointing to a project gathering serious momentum.
"Completing the first phase of dewatering the Main Pit is a massive achievement and the next significant step in our development of the Youanmi Gold Mine."
— Phill Wilding, Managing Director & CEO, Rox Resources
The dewatering of the Main Pit represents arguably the headline event of this update. With the pit floor now fully visible and the historic Main Decline exposed, Rox has cleared one of the most operationally complex hurdles on its road to production.
Key points from this milestone include:
This transition from open pit dewatering to underground dewatering signals a critical operational handoff. Furthermore, it demonstrates that Rox is shifting from preparatory groundwork to active underground mining at a second operating front within Youanmi.
Dewatering in a mining context refers to the controlled removal of groundwater from mine working areas so that safe and efficient mining can proceed. In open pit environments, pumps remove water from the base of the pit. When transitioning to underground operations, however, this process must shift to managing water within the tunnel and decline network — a more technically demanding task.
For investors, the completion of open pit dewatering and the commencement of underground dewatering directly unlocks access to the ore bodies that sit beneath the existing pit floor. Without it, underground development and ore extraction cannot proceed safely.
Key Mining Terms:
| Term | Definition |
|---|---|
| Decline | A sloping underground tunnel used to access deeper ore zones |
| Portal | The entrance to an underground tunnel or decline |
| Development jumbo | A drilling machine used to blast and excavate underground tunnels |
| Return air rise | A vertical shaft that forms part of the underground ventilation circuit |
| Ore drive | An underground tunnel developed along an ore lode for extraction |
| g/t Au | Grams of gold per tonne — the standard measure of gold grade |
The significance of underground dewatering extends beyond mere operational necessity. It represents the gateway to accessing higher-grade ore zones typically found at depth, which often form the economic backbone of underground mining operations.
While Main Pit preparations dominate the headlines, Rox's United North operation is delivering results that would stand out in any mining update. The April performance, consequently, demonstrates both operational efficiency and geological validation of the project's underlying assumptions.
Key United North highlights for April:
Sampling Results — First Ore Lode, United North 2341mRL:
| Sample Interval | From (m) | To (m) | Width (m) | Grade (g/t Au) | Grade x Width (g.m) |
|---|---|---|---|---|---|
| Full interval | 9.00 | 11.20 | 2.20m | 4.99 g/t Au | 10.98 |
| Including (footwall contact) | 9.00 | 9.50 | 0.50m | 8.32 g/t Au | 4.16 |
The first ore lode maintains a visually controllable mining width, described as an important characteristic for efficient underground extraction. The results align with model expectations, providing early validation of the resource model at this level.
The second ore lode at the 2341mRL level has also been intersected, with mapping and sampling completed and assays pending. Visual differences from the surrounding rock and a distinct footwall contact have been noted — mirroring the characteristics of the first ore lode. Results are expected shortly.
Ore drive development and the commencement of ore stockpile building are planned imminently, marking the transition from exploration to production-focused activities.
Alongside underground progress, surface infrastructure is advancing across multiple workstreams simultaneously. The pace of infrastructure development reflects the project's transition from planning to execution phase.
Following receipt of Mine Development and Closure Proposal (MDCP) approval, contractors have mobilised to site and commenced bulk earthworks. Topsoil has been cleared and the first pad is under construction. Interquip is expected to mobilise to site in late May, marking the commencement of formal processing plant construction. Works Approval is currently under assessment by DWER.
All buildings for the accommodation village are now on-site. The expansion has delivered an additional 300 rooms, comprising:
This expansion builds upon the existing 51 rooms from the historic camp, bringing total accommodation capacity on completion to 351 rooms.
| Contractor | Scope | Status |
|---|---|---|
| Pacific Energy Pty Ltd (PEL) | Build Own Operate (BOO) power station — 27MW thermal, 26MWdc solar, 9.3MVA battery | Preferred contractor engaged |
| Lambron Contracting Pty Ltd | Bulk earthworks on-site | Awarded and mobilised April |
| Glencore Technology Pty Ltd | Ultrafine Grind and Albion Process — supply, licensing and support | Contract executed, long lead items ordered |
| K-Drill Pty Ltd | Underground diamond drilling | Preferred contractor, first machine arriving May |
| Interquip | EPC processing plant | Contract in progress, mobilisation late May |
The engagement of an experienced independent power provider delivering a hybrid thermal-solar-battery power solution reflects the scale of infrastructure being built at Youanmi. In addition, borefields drilling has also commenced to increase water availability for future operational requirements.
Rox has maintained its stated development timeline, with key milestones tracking as outlined in the company's pathway to production framework.
| Milestone | Status | Timeline |
|---|---|---|
| Definitive Feasibility Study released | Completed | November 2025 |
| $200m Placement + $18m SPP equity raise | Completed | December 2025 |
| $350m Debt Financing facilities secured | Completed | March 2026 |
| MDCP approval for processing plant and tailings | Completed | March 2026 |
| Final Investment Decision (FID) approved | Completed | March 2026 |
| Main Pit dewatering completed | Completed | May 2026 |
| United North underground development | Ongoing | Record advance rates |
| Processing plant bulk earthworks commenced | Underway | May 2026 |
| Main and Pollard declines commencement | Expected | Late May 2026 |
| Processing plant construction commencement | Expected | June 2026 |
"The team has been hard at work at Youanmi, advancing our pathway to production on-schedule and reinforcing Rox's position as one of Western Australia's next high-grade gold producers."
— Phill Wilding, Managing Director & CEO
The high-level project timeline points toward first gold in late 2027, following mill construction and commissioning through the second and third quarters of that year. Consequently, the ROX Resources Youanmi Gold Mine main pit dewatered and underground development update solidifies the company's position as one of the most advanced gold developers currently operating on the ASX.
For investors tracking Rox Resources, the coming weeks and months present multiple near-term catalysts.
These catalysts represent material de-risking events and operational progress indicators that could influence investor perception of execution capability and timeline adherence.
Rox Resources' appeal as an investment opportunity rests on several interconnected pillars that this operational update reinforces.
Youanmi hosts a global mineral resource of 12.1 million tonnes at 5.6g/t for 2.2 million ounces of gold — a high-grade figure by global standards. This resource base underpins the economic rationale of the project and supports the capital investment being deployed.
With $200 million in equity and $350 million in debt financing secured, Rox entered 2026 in a position available to few ASX-listed gold developers: fully funded through to first gold. This substantially de-risks execution compared to peers who may still face capital raising requirements during construction.
The April record of 342 metres of underground advance at United North with a single jumbo — ahead of DFS projections — represents delivered performance rather than projected capability. Early ore intersections confirming the geological model, on-schedule dewatering, and multiple contracted workstreams demonstrate management translating planning into measurable action.
The confirmed first ore lode at 2.20m @ 4.99g/t Au, including 0.50m @ 8.32g/t Au at the footwall contact aligns with the high-grade character of Youanmi and validates the near-term ore extraction thesis. These grades support the economic assumptions underlying the project's feasibility study.
Beyond production ramp-up, Rox retains exploration upside across a 40km strike length of the Youanmi Greenstone Belt. With diamond drilling commencing and airborne magnetic survey results under review, resource growth potential exists at depth and along strike from current defined mineralisation.
Key Investment Considerations:
The combination of a large high-grade gold resource, demonstrated execution capability, and full funding through to production positions Rox Resources as a differentiated opportunity within the ASX gold development sector.
For investors seeking exposure to near-term gold production with exploration upside, the ROX Resources Youanmi Gold Mine main pit dewatered and underground development update presents a compelling proposition supported by measurable operational progress and a clear pathway to cash flow generation. The next several months represent a critical period where construction momentum and underground development results could significantly influence the investment thesis.
With the Main Pit dewatered, record underground advance rates at United North, and processing plant construction set to begin, Rox Resources (ASX: RXL) is rapidly closing in on becoming one of Western Australia's next high-grade gold producers. Fully funded through to first gold and delivering on schedule across every major milestone, this is a project with genuine momentum behind it. To learn more about Rox Resources, the Youanmi Gold Mine, and what this development pipeline could mean for investors, visit the official company website at roxresources.com.au.