Rox Resources Secures Native Title Agreement With Badimia Barna at Youanmi
Rox Resources (ASX: RXL) has released a comprehensive Rox Resources Youanmi Gold Mine development update and first gold timeline, confirming meaningful progress across underground mining, surface infrastructure, and contract execution. With ore stockpiles building, bulk earthworks nearly complete, and a fixed-cost EPC contract now signed for the processing plant, the company is systematically converting its Definitive Feasibility Study into operational reality — with first gold targeted for mid-CY2027.
What makes this update particularly compelling is the breadth of concurrent activity. Rox is not advancing a single work front — it is simultaneously prosecuting three separate underground mining portals, building surface infrastructure for a full processing plant, and running diamond drilling programmes to extend mine life.
Each workstream reinforces the others, and together they paint a picture of a development project firing on all cylinders.
Management Perspective
"As we track closer to our target of first gold pour by next year, we are confident in our position as one of Western Australia's next high-grade gold producers."
— Phill Wilding, Managing Director & CEO, Rox Resources
One of the headline developments is the progression toward three active ore sources within the Youanmi underground complex. Each front plays a distinct role in building the pre-production ore stockpile and supporting steady-state throughput once the mill is commissioned.
United North commenced in November 2025 and remains the most advanced of the three fronts. Key developments this month include:
The historic Youanmi Decline — originally developed in the 1990s and previously mined to approximately 630 metres below surface — is being rehabilitated rather than replaced with a new decline. This is a deliberate and cost-efficient decision:
The Pollard Decline adds a third planned ore source to the operation:
| Mining Front | Status | Key Milestone |
|---|---|---|
| United North | Active — ore drives underway | Record 343m advance in May 2026 |
| Youanmi Decline | Stripping commenced | Mining activities from October 2026 |
| Pollard Portal | Face support underway | Firing to commence within weeks |
A standout milestone in this update is the execution of the Engineering, Procurement and Construction (EPC) contract with Interquip for the processing plant. This is more than an administrative step — it is a significant risk-reduction event for investors evaluating the project's capital delivery profile.
Key points on the EPC contract:
The Managing Director specifically noted that fixing the majority of prices across all major contracts "provides increased certainty that pre-production expenditure will be in line with our estimates in the DFS" — a direct and unambiguous message to investors tracking capex execution.
Concept Explained: EPC (Engineering, Procurement and Construction) Contract
An EPC contract is an agreement under which a single contractor takes responsibility for designing, procuring materials for, and constructing a facility — in this case, a gold processing plant — for a predetermined price.
For investors, the significance is straightforward:
| Term | Definition |
|---|---|
| EPC Contract | Engineering, Procurement and Construction — a fixed-price contract covering design, materials procurement and build |
| DFS (Definitive Feasibility Study) | A detailed technical and financial study confirming the economic viability of a mining project |
| ROM (Run-of-Mine) | Ore extracted directly from underground workings before any processing |
| MRL (Metres Reduced Level) | A depth measurement in metres relative to sea level, used to describe underground mine levels |
| MRE (Mineral Resource Estimate) | A formal estimate of the quantity and grade of mineralisation within a deposit |
| Infill Drilling | Drilling within an existing resource area to increase confidence in grade and geometry estimates |
| JORC Code | The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves — the industry reporting standard |
With ore drive development now delivering early wall sampling results at United North, Rox is also launching a structured underground diamond drilling programme with two clear objectives.
Early wall sampling results from United North ore drives are confirming that the underground ore grade is performing in line with expectations. Significant intersections from underground face sampling at the 2341mRL level include:
| Sample ID | Interval (m) | Grade (Au g/t) | Au Grade x Metres |
|---|---|---|---|
| UNN_2341_XCT_WS_F2_S | 3.40 | 3.88 g/t | 13.20 g.m. |
| UNN_2356_ACC_WS_F1_N | 2.20 | 4.55 g/t | 10.01 g.m. |
| UNN_2341_ODS1_F2_A | 0.70 | 9.44 g/t | 6.61 g.m. |
| UNN_2341_XCT_WS_F2_N | 1.00 | 3.50 g/t | 3.50 g.m. |
| UNN_2356_ACC_WS_F1_S | 1.00 | 3.07 g/t | 3.07 g.m. |
The company notes that most ore drive assays remain outstanding, meaning the full picture of ore grade performance across current development headings is yet to be reflected. The DFS MRE geological model is tracking well against actual mined grades based on results received to date.
The Rox Resources Youanmi Gold Mine development update and first gold timeline represents a well-sequenced progression from feasibility to first gold. Furthermore, the milestones achieved to date are substantial, and the remaining steps are clearly defined.
| Phase | Timeframe |
|---|---|
| Mill construction and commissioning | CY2026–CY2027 |
| Extensional drilling (surface and underground) | CY2026 onwards |
| Resource definition drilling (underground) | CY2026 – mid-CY2027 |
| Tailings, power station, oxygen facility construction | CY2026–CY2027 |
| Underground mining — building to steady production | CY2026–CY2027 |
| First gold pour (target) | Mid-CY2027 |
Rox Resources occupies an increasingly rare position in the Australian gold development landscape — a company with a fully funded, high-grade project actively under construction, with contracts largely locked in and multiple ore sources advancing simultaneously.
The investment case rests on several compounding strengths:
The Youanmi Gold Project hosts a global Mineral Resource of 12.1 million tonnes at 5.6 g/t for 2.2 million ounces of gold. At that grade, Youanmi sits comfortably in the high-grade tier of Australian gold projects — a characteristic that underpins operational margins and capital efficiency.
With $200 million in equity raised and $350 million in debt financing secured, the funding architecture to deliver Youanmi to production is in place. In addition, the execution of fixed-cost contracts across major works packages reinforces confidence that the capital plan will be met.
Three simultaneous ore development fronts — United North (active), Youanmi Decline (October 2026), and Pollard (imminent) — provide scheduling flexibility and reduce dependency on any single ore source.
United North is advancing at rates above DFS assumptions, with 343 metres in May using just one development jumbo. This is a tangible early indicator that the underground operation can meet or exceed its planned productivity targets.
Fixed-price contracting for the processing plant, combined with DFS-aligned pricing across remaining major supply contracts, signals disciplined financial management and reduces the risk of budget overruns.
As the Youanmi Gold Mine transitions from development to production, the newsflow profile for Rox is set to intensify. Each of the following represents a near-term catalyst worth monitoring:
Consequently, the Rox Resources Youanmi Gold Mine development update and first gold timeline continues to demonstrate that the project is firmly on track, with each passing milestone reinforcing confidence in the mid-CY2027 target.
Key Takeaway:
Rox Resources has positioned itself as one of Western Australia's next high-grade gold producers, with a 2.2 million ounce resource at 5.6 g/t, a fully funded development programme, and three underground ore fronts now advancing simultaneously. With a fixed-cost EPC contract signed, mill earthworks nearly complete, and first gold targeted for mid-CY2027, the project is tracking its DFS milestones — and investors should be watching closely as the construction and ore stockpile build gathers pace.
Rox Resources (ASX: RXL) is advancing the Youanmi Gold Mine on multiple fronts simultaneously — with three underground ore sources in development, a fixed-price EPC contract signed, and first gold targeted for mid-CY2027. For investors seeking exposure to a fully funded, high-grade Australian gold development project that is actively converting feasibility into construction reality, the full details on the company and its flagship project are available at roxresources.com.au.