Quantum Graphite Hits 80% Plant Design as Uley 2 FEED Tracks Toward Construction
Key Takeaways
- Process plant design for the Uley 2 Project is 80% complete and the costs review updating the 2023 Definitive Feasibility Study is 75% complete, with both workstreams progressing on schedule.
- The FEED study has confirmed the original process plant design as specified in the 2023 DFS — no redesign has been required, reducing execution risk and protecting the cost and schedule baseline.
- The Environmental Impact Study for the Al Buraimi, Oman refinery site is 100% complete, with LIDAR survey, land surveys, and hydrology and geotechnical phases now scheduled to follow.
- Site location for the South Australian plant was re-evaluated following the 20-year Ore Supply Agreement announced 12 June 2026, specifically to ensure future expansion can be expedited without disrupting existing operations.
- Lease negotiations with Madayn, Oman's industrial land agency, are described as "well progressed," with incentive structures being negotiated to support the refinery precinct and its long-term expansion plans.
Uley 2 project FEED advances on schedule as plant design reaches 80% completion
Quantum Graphite Limited‘s Front-End Engineering and Design (FEED) program for the Uley 2 Project is progressing as scheduled, with two parallel workstreams moving forward concurrently across South Australia and Oman. Process plant design stands at 80% complete, costs review at 75% complete, and the first stage of the geotechnical workstream is scheduled to commence within 4 weeks. The program is being undertaken within the framework of the integrated downstream structure established under the Sunlands Pure Group, which consolidates processing and refining across two nodes: flake concentrate production on the Southern Eyre Peninsula and refining at Al Buraimi, Oman.
| Workstream | Location | Status | Completion % | Next Step |
|---|---|---|---|---|
| Process plant design | Southern Eyre Peninsula, SA | Well advanced | 80% | Ongoing |
| Costs review (updating 2023 DFS) | Southern Eyre Peninsula, SA | Well advanced | 75% | Complete capital and operating cost update |
| Geotechnical workstream | Southern Eyre Peninsula, SA | Scheduled | Not commenced | Commence first stage within 4 weeks |
| Environmental Impact Study | Al Buraimi, Oman | Completed | 100% | LIDAR survey program |
| Site lease negotiations (Madayn) | Al Buraimi, Oman | Well progressed | Ongoing | Conclude key lease terms and incentive structure |
When big ASX news breaks, our subscribers know first
What FEED means for investors — and why it matters at this stage
Front-End Engineering and Design (FEED) is the engineering phase that sits between a completed feasibility study and actual construction. In plain terms, it takes the technical blueprint produced by a feasibility study and translates it into a fully engineered, costed, and schedulable project that is ready for contractor bids.
Here is what that process typically involves:
- Finalising process flow diagrams and plant layout to construction-ready specification
- Completing a detailed cost and schedule estimate that updates prior feasibility figures
- Producing the engineering definition required to negotiate engineering, construction and procurement (EPC) bids
The practical significance for investors is that FEED completion enables, as the announcement states, a “clean transition to project execution.” A project exiting FEED with confirmed design and updated costs is meaningfully closer to construction than one still working through feasibility. It de-risks the capital deployment decision by removing engineering uncertainty before any major spending commitment is made.
One notable point from this update: the FEED study has confirmed the process plant design as originally specified in the 2023 Definitive Feasibility Study (DFS), including the original 2019 DFS. No redesign has been required. That is a positive signal, as design changes at this stage typically carry cost and schedule consequences. The confirmation of the original design reduces execution risk heading into the next phase.
Two-node progress — Eyre Peninsula plant and Oman refinery site advancing in parallel
Southern Eyre Peninsula — mine and process plant
Engineering works completed to date across the South Australian workstream include comprehensive process flow diagrams, piping and instrumentation (P&ID) drawings, and a complete three-dimensional layout of the process plant.
The site location for the plant was also re-evaluated following the finalisation of the 20-year Ore Supply Agreement (announced 12 June 2026). The re-evaluation was specifically to ensure that future expansion of the operation could be expedited without impacting existing operations — a forward-thinking design consideration that builds flexibility into the project’s footprint from the outset.
Key figures from this workstream:
- Plant design: 80% complete
- Costs review updating the 2023 DFS capital and operating costs: 75% complete
- Geotechnical workstream: scheduled to commence within 4 weeks
Al Buraimi, Oman — refinery site preparation underway
Following the completion of the Environmental Impact Study for the refinery site (announced 29 June 2026), site preparatory works have been scheduled. The sequence of planned activities is:
- LIDAR survey program to produce high-resolution three-dimensional mapping of the 2,600,000m² site
- Land surveys and preparation of detailed survey plans for the whole site
- Hydrology and geotechnical phases, which depend on the survey outputs above
Lease negotiations with Madayn, Oman’s industrial land agency, are described as “well progressed.” The terms being negotiated will include incentives explicitly structured to support the refinery precinct plan and its long-term expansion plans. The involvement of the host country’s industrial land agency in structuring incentives around the refinery is relevant context when assessing sovereign support and project risk at this location.
The next major ASX story will hit our subscribers first
What comes next — from FEED completion to project execution
When the FEED program concludes, the Uley 2 Project will have its final engineering definition in place. That means a completed detailed design, an updated cost and schedule estimate, and the documentation required to negotiate EPC bids with construction contractors. These outputs represent the commercial bridge between engineering and shovels in the ground.
The company has indicated it expects to make further announcements as the FEED progresses. No specific completion dates for the FEED program were provided in the announcement.
The commercial destination that gives this engineering work its strategic purpose is the integrated Sunlands Pure Group structure: flake concentrate produced on the Eyre Peninsula, refined at Al Buraimi, and supplied to manufacturers in the Li-ion battery anode, isostatic graphite, and thermal energy storage markets. The Sunlands Pure Group technologies are capable of purifying natural flake graphite to 99.9% graphitic carbon purity. The parallel progress across both nodes reflects the integrated nature of that commercial model — progress at one site is structurally linked to readiness at the other.
Don’t Miss the Next ASX Mining Breakout
Get FREE breaking ASX mining news delivered to your inbox within minutes of release, complete with in-depth analysis. Join 30,000+ subscribers already ahead of the market. Click the “Free Alerts” button at Discovery Alert to ensure the next market-moving announcement lands in your inbox the moment it drops.