Pure One’s Venus-2H Logs 445m of Coal With Gas Shows Peaking at 42.3%

Pure One Corporation's Venus-2H horizontal well has reached total depth of 1,450m, intersected the Venus-1 vertical wellbore, and recorded Pure One Venus-2H gas shows peaking at 42.3% across 445 metres of interpreted net Macalister Lower coal — setting up the project's first real commercial test via dewatering and flow testing.
By William Hadrian -
  • Venus-2H reached total depth of 1,450m and successfully intersected the Venus-1 vertical wellbore at approximately 927m measured depth, establishing the integrated well system required for dewatering and flow testing.
  • Gas shows peaked at 42.3% in the second sidetrack — well above the 8% threshold classified as excellent under the wellsite rating system — with almost all recorded readings across all three wellbore sections rated excellent.
  • The well encountered a cumulative 445m of interpreted net Macalister Lower target coal, including a continuous 148m interval between 1,181m and 1,329m measured depth in the second sidetrack.
  • Operations now shift to well completion, rig demobilisation, and installation of surface production and water-handling equipment ahead of the dewatering and flow testing programme — the first real measure of commercial potential.
  • Pure One holds a 69.4% interest in Project Venus, operated by Eastern Gas Corporation (ASX: EGA), with flow test results representing the next material value catalyst for the stock.
Summarise with AI:

Pure One’s Venus-2H well hits total depth with excellent gas shows peaking at 42.3%

Pure One Corporation‘s 69.4%-owned Venus-2H horizontal appraisal well at Project Venus in Queensland’s Surat Basin has reached total depth of 1,450m and successfully intersected the existing Venus-1 vertical wellbore. The well, operated by Eastern Gas Corporation (ASX: EGA), intersected Venus-1 at approximately 927m measured depth (approximately 426m vertical depth) and encountered a cumulative 445m of interpreted net Macalister Lower target coal. Gas shows recorded throughout the target intervals peaked at 42.3%, with almost all readings classified as excellent under the wellsite rating system. The successful intersection advances Project Venus toward its first meaningful reservoir assessment via dewatering and flow testing, the stage that will provide the first real measure of the reservoir’s commercial potential.

Venus-1 intersection establishes the integrated well system

The subsurface connection between Venus-2H and Venus-1 was achieved through a refined drilling sequence:

  1. The first sidetrack commenced from approximately 775m measured depth to refine the well trajectory and achieve the planned intersection
  2. Venus-2H successfully intersected the Venus-1 vertical wellbore at approximately 927m measured depth (approximately 426m vertical depth)
  3. Following confirmation of the intersection through drilling indications, the ranging assembly was replaced with a geosteering assembly and drilling continued through the target coal

The intersection establishes the planned subsurface connection between the two wells. Following completion and commissioning, the integrated Venus-2H/Venus-1 well system is designed to enable water and gas entering the Venus-2H horizontal wellbore to flow through Venus-1 to the surface facilities during dewatering and flow testing. That subsurface pathway is what allows the horizontal well to produce through the vertical well’s existing infrastructure, the critical design feature for the testing phase ahead.

445 metres of net target coal and repeated excellent gas shows

Across the original wellbore and two sidetracks, Venus-2H encountered a total of 445m of interpreted net Macalister Lower coal within the current production wellbore. This includes 148m of continuous target coal between 1,181m and 1,329m measured depth in the second sidetrack.

Wellbore Section Total Gas Reading Range Rating
Original wellbore 2.5% – 18.0% Excellent (>8%)
First sidetrack 8.8% – 23.8% Excellent
Second sidetrack 4.5% – 42.3% (well max) Excellent

Under the classification used for the drilling programme, readings above 8% are considered excellent gas shows. Almost all recorded shows were classified as excellent under the wellsite rating system. These readings represent hydrocarbons released from coal cuttings during drilling and detected by the rig’s surface gas-monitoring equipment. Importantly, they confirm the presence of gas within the intersected coal but do not represent gas flow rates or provide a direct measure of future well productivity. That assessment will come from the planned dewatering and production-testing programme.

Venus-2H Gas Shows by Wellbore Section

At approximately 1,117m measured depth in the first sidetrack, Venus-2H exited the Macalister Lower coal seam. Drilling and geosteering data indicated an interpreted fault displacement of approximately 4m. The first sidetrack was extended to better delineate the structure but did not establish sustained re-entry into the target seam. Using the geological and geosteering information obtained from the first sidetrack, the drilling team commenced a second sidetrack from approximately 1,047m measured depth. The second sidetrack re-entered the target coal at 1,061m and, after crossing the interpreted structural displacement, re-entered the Macalister Lower coal seam at 1,181m measured depth.

Understanding coal seam gas and why flow testing matters

Coal seam gas (CSG) is natural gas stored within coal seams, typically adsorbed to the coal surface and held in place by water pressure within the reservoir. For the gas to flow to the surface, that water must be removed first, a process called dewatering. Reducing the reservoir pressure allows the gas to desorb from the coal and begin flowing.

The horizontal well at Venus-2H intersects the coal seam over a long interval, providing multiple contact points with the gas-bearing rock. The connection to Venus-1 allows water and gas entering the horizontal section to flow through the vertical well to surface facilities, where production rates can be measured and controlled.

Gas shows, like the 42.3% peak recorded at Venus-2H, confirm gas is present in the coal. But they do not tell you how much gas the reservoir can produce over time, or at what rate. That is what flow testing measures. The test phase ahead will reduce reservoir pressure, trigger gas desorption, and measure how the reservoir responds. That data — water production rates, timing of gas breakthrough, sustained gas flow — is what determines whether the project can deliver commercial production. This is the key value inflection point for Project Venus.

Operations move to completion and flow testing

With Venus-2H having reached total depth, operations now shift to well completion and preparation for testing:

  • Recover the drilling assembly and prepare the wellbore for installation of the planned completion liner, designed to maintain access to the intersected coal intervals and facilitate the flow of water and gas through Venus-2H towards the connection with Venus-1
  • Rig down and demobilise the drilling rig and associated services from site
  • Install and commission the required surface production, water-handling and gas-measurement equipment
  • Commence dewatering of the target coal intervals to reduce reservoir pressure and support gas desorption and flow
  • Measure water production, reservoir pressure response, timing of gas breakthrough and subsequent gas flow performance

Pure One has stated it will provide further updates following completion of the well, commencement of flow testing, and as material test results become available. The successful Venus-1 intersection, 445m of interpreted net target coal and gas shows of up to 42.3% represent important operational milestones. The next phase of dewatering and production testing will provide the first meaningful assessment of the reservoir’s ability to deliver commercial gas. That assessment is the catalyst investors should watch.

Management outlook

Scott Brown, Managing Director

“Pure One is pleased to see the well being drilled to 1,450 metres at Venus-2H. The successful intersection with Venus-1, followed by extended drilling within the target Macalister Lower coal seam, represents an important operational milestone for the program. The drilling results with excellent gas shows peaking at 42.3% and 445 metres of interpreted net Macalister Lower coal seam are very encouraging. The Venus 2H and Venus 1 wells will now be set up for dewatering and flow testing. We are now looking forward to the flow testing with confidence.”

Project Venus sits within Pure One’s broader clean energy portfolio, which includes natural gas projects operated through Eastern Gas (ASX: EGA) and an indirect exposure to Botswana gas via the company’s strategic investment in Botala Energy (ASX: BTE). Pure One also operates in zero-emission mobility and energy solutions, including battery-electric vehicles and battery-swap systems. The Venus flow testing programme represents the next material milestone for the company’s Australian natural gas development pathway.

Get ASX Energy News Before the Market Moves

Join 30,000+ investors receiving FREE breaking ASX energy news within minutes of release, complete with in-depth analysis. Stay ahead on coal seam gas, oil and gas, and energy sector developments by clicking the “Free Alerts” button at Discovery Alert to start receiving real-time alerts the moment market-moving announcements drop.


Frequently Asked Questions

What are gas shows and what do they mean for Pure One's Venus-2H well?

Gas shows are readings of hydrocarbons released from coal cuttings during drilling, detected by surface monitoring equipment on the rig. At Venus-2H, they peaked at 42.3% — well above the 8% threshold classified as excellent — confirming gas is present in the Macalister Lower coal seam, though they do not indicate future production rates.

What is coal seam gas dewatering and why does it matter for Project Venus?

Dewatering is the process of removing water from a coal seam reservoir to reduce pressure, which allows adsorbed gas to desorb from the coal and flow to the surface. For Project Venus, dewatering is the next critical phase after well completion and will provide the first real measure of whether the reservoir can deliver commercial gas volumes.

Why did Venus-2H require two sidetracks during drilling?

The first sidetrack was needed to refine the well trajectory and achieve the planned intersection with Venus-1, but it exited the target Macalister Lower coal seam at approximately 1,117m due to an interpreted fault displacement of around 4 metres. A second sidetrack was drilled from 1,047m using geological data from the first, successfully re-entering the target coal at 1,061m and delivering 148m of continuous coal between 1,181m and 1,329m measured depth.

What happens next for Pure One's Project Venus after reaching total depth?

Operations now move to well completion, including installation of a liner to maintain access to the intersected coal intervals, followed by rig demobilisation and installation of surface production, water-handling, and gas-measurement equipment. Once commissioned, the dewatering and flow testing programme will begin, with Pure One committing to provide updates as material test results become available.

What is Pure One Corporation's ownership stake in Project Venus?

Pure One Corporation (ASX: P1E) holds a 69.4% interest in Project Venus, which is operated by Eastern Gas Corporation (ASX: EGA) in Queensland's Surat Basin.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.