Frontier Energy Clears Key Grid Hurdle for 130MW Waroona Stage Two Solar Project

Frontier Energy Waroona Stage Two has been deemed 'Ready to Progress' by Western Power, clearing a key grid connection gate for the 130MW solar and 80MW battery project 120km south of Perth.
By William Hadrian -
  • Western Power has deemed Waroona Stage Two 'Ready to Progress' under its Critical Projects Framework, opening the door to network studies and assessments on the way to an Access Offer.
  • Stage Two already has Development Approval and completed key environmental studies, leaving grid connection as the main gating item.
  • Stage One's substation and Landwehr Terminal cable, a combined cost of over $30 million, can be reused, which Frontier says means a 'materially reduced timeframe and cost' for Stage Two.
  • Stage Two is planned at 130MW solar and 80MW of roughly eight-hour battery storage, closely mirroring fully funded Stage One, which has first generation scheduled for 2028.
  • No Stage Two cost, funding position or Access Offer timeline was disclosed, and the priority benefit depends on Western Power's requirements being met.

Frequently Asked Questions

What does Ready to Progress status mean for Frontier Energy's Waroona Stage Two?

It means Western Power has determined Stage Two can advance through the Initiation Phase of its grid connection application into network studies and assessments. Frontier expects increased priority and greater visibility on the process, subject to Western Power's requirements being met.

What is Western Power's Critical Projects Framework?

It is the framework under which Western Power assessed Stage Two's grid connection application and made the Ready to Progress determination. Frontier says the outcome recognises Stage Two as a project of strategic importance.

What is an Access Offer in a grid connection process?

An Access Offer is the step Frontier is now advancing towards after network studies and assessments with Western Power. It is the pathway to connecting Stage Two to the South West Interconnected System (SWIS).

How big is Frontier Energy's Waroona Stage Two project?

Stage Two is planned at 130MW of solar capacity and an 80MW battery of roughly eight hours' duration. It sits alongside Stage One's 132MW solar and 81.5MW battery on an 830-hectare site about 120km south of Perth.

When will Frontier Energy's Waroona Stage Two be built?

No timeline for the Access Offer or Stage Two construction has been given. Stage One is scheduled for first generation in 2028, and Stage Two is expected to benefit from reused substation and cable infrastructure.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.

About the Publisher