Invictus Energy Clears Musuma-1 Wellpad as Zimbabwe Drilling Nears November Spud
Key Takeaways
- Exalo Drilling has formally inspected, accepted and signed off the Musuma-1 wellpad, clearing a key prerequisite for moving the rig.
- Musuma-1 remains on track to spud in November at the 80%-owned and operated Cabora Bassa Project in Zimbabwe.
- Exalo Rig 202 relocates from Mukuyu-2, then needs rig-up, remaining maintenance and final acceptance before drilling begins.
- No rig move date, drilling results, resource volumes or funding details were disclosed, so the November spud is the main marker to track.
- The Cabora Bassa portfolio covers 360,000 hectares and includes the Mukuyu Gas Field and multiple Basin Margin prospects.
Musuma-1 wellpad completed and accepted by Exalo
Invictus Energy has completed the Musuma-1 wellpad, and drilling contractor Exalo Drilling S.A. (“Exalo”) has formally inspected, accepted and signed it off. In an operational update dated 15 October 2026, the company said this clears a key prerequisite for moving the rig.
The setting is the 80%-owned and operated Cabora Bassa Project in Zimbabwe. Musuma-1 remains on track to spud (begin drilling) in November.
For investors, a signed-off wellpad removes a logistical hurdle between the company and first drilling at the Musuma-1 exploration target. Key highlights from the update:
- Wellpad construction completed, including all associated civil works and access road upgrades
- Formal acceptance and sign-off by Exalo
- Exalo Rig 202 to relocate from Mukuyu-2 to Musuma-1
- Final rig acceptance to follow rig-up and remaining rig maintenance, before drilling begins
Scott Macmillan, Managing Director
“The completion and formal acceptance of the Musuma-1 wellpad by Exalo represents another important milestone in our preparations for the upcoming drilling campaign.”
When big ASX news breaks, our subscribers know first
Rig 202 move and the path to spud
The wellpad is done, but the rig still has to get there and be signed off. The announcement lays out the order of work clearly.
Remaining steps before drilling
Following relocation, Exalo will undertake the steps below:
- Rig move from Mukuyu-2 to Musuma-1
- Rig-up activities
- Completion of the remaining planned rig maintenance and preparation works
- Final rig inspection and acceptance
- Commencement of drilling operations
The announcement does not disclose a specific rig move date. The only timing given is the November spud target.
| Milestone | Status |
|---|---|
| Wellpad and civil works | Completed |
| Exalo acceptance | Completed |
| Rig move | Next |
| Rig-up and maintenance | Pending |
| Final rig acceptance | Pending |
| Spud | Targeted **November** |
Macmillan said the company’s operational focus is “now firmly on the rig move, rig-up and completion of the remaining maintenance activities…” The announcement also includes aerial and wellsite figures showing the rig pad, cellar, mud pump lay down area, water supply and waste pit.
Why Musuma-1 matters in the Cabora Bassa Basin
What is an exploration well?
An exploration well tests whether oil or gas is present in a target that has not yet been drilled. Until the wellpad and rig are ready, drilling cannot start, which is why these steps matter.
Hitting the schedule is therefore a key near-term marker, and the well itself will test the company’s exploration thinking.
Investment context
Invictus has made a significant gas discovery at the Mukuyu field in the Cabora Bassa Basin in northern Zimbabwe, described in the announcement as “one of the last untested large frontier rift basins in onshore Africa”. The portfolio covers 360,000 hectares across SG 4571 and EPOs 1848/49, containing the Mukuyu Gas Field and multiple Basin Margin prospects.
Macmillan described Musuma-1 as an “exciting, high-impact exploration target”. The company notes its Prospective Resource estimates are unrisked, and it is not certain that these resources will be commercially viable to produce. This announcement gives no resource volumes.
The next major ASX story will hit our subscribers first
What should investors watch next?
The next milestones are the rig move from Mukuyu-2, completion of rig-up and maintenance, final rig acceptance, and the spud targeted for November.
Macmillan said the schedule remains on track. The announcement discloses no drilling results, resource upgrades or funding details, so the schedule is the main thing to track for now.
For readers wanting to follow the drilling schedule from the start, our detailed coverage of the Musuma-1 spud timetable sets out how the November 2026 target was first confirmed and what the campaign sequence involves.