Forrestania Resources Advances Lake Johnston Gold Plant Toward First Pour
Mont Royal Resources Limited (ASX: MRZ, TSXV: MRZL) has released an updated Preliminary Economic Assessment (PEA) for its 100%-owned Ashram Rare Earths and Fluorspar Project in Nunavik, Québec, Canada. The Mont Royal Resources Ashram rare earth project updated PEA results make a compelling case for one of North America's most significant undeveloped rare earth deposits.
The updated study, completed by Altris Engineering in accordance with NI 43-101 standards, confirms Ashram as a large-scale, long-life rare earth development with robust project economics, a competitive cost profile, and meaningful expansion optionality beyond the base case.
With a pre-feasibility study (PFS) targeted to commence in H2 CY2026, the company is moving with purpose toward the next stage of development.
Managing Director Nicholas Holthouse stated: "The updated PEA marks a major step forward for the Ashram Project, confirming a large-scale, long-life development with strong underlying economics and a clear pathway to advancement. The study has highlighted Ashram's combination of scale, favourable mineralogy and competitive cost profile, supporting its potential to become a meaningful long-term supplier of rare earth products into Western supply chains."
The headline economics of the Mont Royal Resources Ashram rare earth project updated PEA results are summarised below:
| Economic Metric | Unit | Value |
|---|---|---|
| LOM Revenue | CAD M | 24,638 |
| LOM EBITDA | CAD M | 15,460 |
| EBITDA Margin | % | 62.7% |
| LOM Undiscounted Post-Tax Cash Flow | CAD M | 8,365 |
| Post-Tax NPV (8% real) | CAD M | 2,026 |
| Pre-Tax NPV (8% real) | CAD M | 3,440 |
| Post-Tax IRR (real) | % | 22.0% |
| Pre-Tax IRR (real) | % | 25.6% |
| Post-Tax Payback from Production | Years | 3.9 |
The project carries an initial capital cost of CAD$1.23 billion (including a 30% contingency), with total life-of-mine capital expenditure estimated at CAD$1.605 billion.
Furthermore, the project is anticipated to qualify for approximately CAD$342 million in refundable Clean Technology Manufacturing Investment Tax Credits (CTM ITC), which are incorporated into post-tax cash flows.
The Ashram Project is designed around a conventional open-pit operation with an initial nameplate throughput of approximately 1.8 million tonnes per annum (Mtpa), supported by a highly favourable strip ratio of just 0.4:1. This means very little waste rock needs to be moved relative to ore mined.
Production highlights over the 30-year mine life include:
The 30-year mine plan uses only approximately 25% of the current global resource, highlighting substantial long-term expansion optionality.
Of the approximately 53 Mt of mill feed underpinning the production target, 93% is sourced from Indicated Mineral Resources, providing a high level of geological confidence in the near-term mine schedule.
A Preliminary Economic Assessment (PEA) is an early-stage technical and economic evaluation of a mineral project designed to determine whether a project has sufficient economic merit to justify further, more detailed study.
Key characteristics investors should understand:
A PEA with strong economics signals that a project has the fundamental scale and economic characteristics to attract further investment and advance toward development. It represents an important de-risking milestone that increases confidence and broadens the potential investor and partner base.
| Term | Definition |
|---|---|
| NPV (Net Present Value) | The present value of future cash flows discounted at a set rate (here, 8%). A positive NPV indicates the project creates value above its cost of capital. |
| IRR (Internal Rate of Return) | The discount rate at which NPV equals zero. A higher IRR indicates stronger returns relative to capital invested. |
| EBITDA | Earnings before interest, taxes, depreciation and amortisation — a measure of operating profitability. |
| REO | Rare Earth Oxide — the form in which rare earth elements are typically measured and sold. |
| NdPr | Neodymium-praseodymium — high-value magnet rare earths used in EVs, wind turbines and defence applications. |
| TREO | Total Rare Earth Oxide — the combined grade of all rare earth oxides present in the ore. |
| Strip Ratio | The ratio of waste rock to ore that must be mined. A low strip ratio (0.4:1) means minimal waste removal, reducing mining costs. |
| C1 Cash Cost | The direct cash cost to produce one kilogram of saleable REO, excluding sustaining capital. |
| AISC | All-In Sustaining Cost — C1 cash cost plus sustaining capital, providing a more complete view of the true cost of production. |
Ashram's cost profile is one of the study's standout features, supported by the deposit's low strip ratio, favourable mineralogy, and integrated processing strategy.
| Unit Cost Metric | Value |
|---|---|
| C1 Cash Cost | CAD$17.99/kg saleable REO |
| All-In Sustaining Cost (AISC) | CAD$18.58/kg saleable REO |
The relatively tight spread between C1 and AISC reflects the capital-efficient nature of the operation. The low strip ratio of 0.4:1 significantly reduces mining costs relative to comparable open-pit rare earth operations.
In addition, the production of a high-grade rare earth concentrate (approximately 30% REO) reduces the complexity and cost burden on the downstream hydrometallurgical refinery. Average annual operating costs are estimated at CAD$306 million, with total life-of-mine operating expenditure of CAD$9,178 million.
The development strategy for Ashram is designed around a two-facility model that separates mining and concentration from downstream refining, improving logistics flexibility and reducing development complexity.
The intermodal logistics corridor runs from Ashram via a 320km road link to Schefferville, connecting to existing rail infrastructure to Sept-Îles, and onward approximately 570km to Saguenay by road or marine transport along the St. Lawrence River.
The Mont Royal Resources Ashram rare earth project updated PEA results are underpinned by an updated JORC Mineral Resource Estimate (MRE) released on 1 October 2025, which remains one of the largest undeveloped rare earth resource bases in North America.
| Category | Tonnes (Mt) | TREO Grade (%) | NdPr/TREO (%) |
|---|---|---|---|
| Indicated | 73.2 | 1.89% | approximately 21.2% |
| Inferred | 131.1 | 1.91% | approximately 21.4% |
| Total | 204.3 | approximately 1.90% | — |
Key resource characteristics include:
The 30-year PEA mine plan draws on only approximately 25% of the total global resource, meaning the deposit's full potential remains largely untapped at the PEA stage.
The PEA includes a single-variable sensitivity analysis, flexing key assumptions ±30% from the base case. Results confirm the project maintains meaningful positive NPV across a range of adverse scenarios.
| Variable | -30% NPV (CAD M) | Base Case NPV (CAD M) | +30% NPV (CAD M) |
|---|---|---|---|
| REO Basket Price / Recovery / Payability | 667 | 2,026 | 3,354 |
| Operating Cost | 2,518 (at -30%) | 2,026 | 1,522 (at +30%) |
| Initial Capital Cost | 2,220 (at -30%) | 2,026 | 1,830 (at +30%) |
| Diesel Fuel Price | 2,030 (at -30%) | 2,026 | 2,022 (at +30%) |
The project's greatest sensitivity lies on the revenue side — REO basket price, recovery rates and payability factors each directly multiply into project revenue.
However, even under a 30% reduction in basket prices, the project retains a post-tax NPV of CAD$667 million, indicating a degree of economic resilience at the PEA level.
Ashram is entering development at a time when Western governments and industries are actively seeking to reduce dependence on Chinese rare earth supply chains. China accounted for approximately 77% of global rare earth mine production and approximately 90% of separation capacity in 2025.
Demand fundamentals for magnet rare earths are compelling:
PEA pricing was based on independent forecasts from Adamas Intelligence (Q1/Q2 2026 Rare Earth Pricing Quarterly Outlook). For context, key near-term pricing assumptions include:
| Rare Earth Oxide | 2026 Price (US$/kg) | 2031–2035 Avg (US$/kg) |
|---|---|---|
| Nd₂O₃ | 125.00 | 172.73 |
| Pr₂O₃ | 125.93 | 174.01 |
| Tb₂O₃ | 1,700.00 | 1,950.40 |
| Dy₂O₃ | 420.00 | 517.60 |
| Y₂O₃ | 35.00 | 22.00 |
The company's proposed MREC product is considered suitable for processing by North American and European rare earth separation facilities. No offtake agreements are currently in place, with engagement ongoing.
The Mont Royal Resources Ashram rare earth project updated PEA results are deliberately conservative, capturing only a fraction of Ashram's total potential. Several value-adding opportunities sit outside the current study scope:
Fluorspar recovery circuit — Ashram hosts significant fluorspar mineralisation. A dedicated recovery circuit is excluded from the current flowsheet but is being advanced for inclusion in future studies, with potential to add meaningful by-product revenue.
BD-Zone inclusion — The BD-Zone, an additional REE-bearing unit, was excluded from the current MRE pending metallurgical evaluation. Successful test work could add to the resource base and mine plan.
Resource expansion drilling — Mineralisation remains open laterally and at depth. Additional drilling across the Eldor Carbonatite Complex, including the Mallard satellite target, could extend mine life well beyond 30 years.
Downstream and strategic partnerships — The company is actively engaging with potential offtake and strategic partners, with the Saguenay refinery concept providing a natural integration point for downstream value capture.
Infrastructure cost optimisation — A regional shared infrastructure strategy is being evaluated in collaboration with other mining projects, government agencies, and First Nations, which could reduce access road costs relative to the standalone assumption used in the PEA.
With the updated PEA now complete, Mont Royal has a clear sequence of workstreams planned to advance the project toward a Pre-Feasibility Study and beyond.
| Workstream | Target Timeline |
|---|---|
| Pre-Feasibility Study (PFS) commencement | H2 CY2026 |
| Metallurgical optimisation and flowsheet refinement | Ongoing |
| Environmental baseline and permitting programs (Ashram & Saguenay) | Ongoing |
| Fluorspar recovery circuit test work | Upcoming |
| BD-Zone test work and MRE potential inclusion | Upcoming |
| Offtake, downstream and strategic partnership engagement | Ongoing |
| Regional shared infrastructure evaluation | Ongoing |
The PFS will be a critical value-creation milestone, lifting the study accuracy from ±50% (PEA level) to ±25% and providing a more robust basis for investment and financing decisions.
Permitting is expected to take several years and will span federal and Québec provincial frameworks, covering mine operations, the Ashram–Saguenay logistics corridor, and the downstream refinery. Early stakeholder engagement with Inuit, Naskapi and Innu communities is already underway.
Mont Royal Resources presents a rare combination of scale, jurisdiction quality, product basket relevance, and project stage for investors seeking exposure to the structural growth in rare earth demand.
The core investment case rests on several pillars:
Discovery Alert's proprietary Discovery IQ model delivers real-time alerts on significant ASX mineral discoveries, transforming complex data across more than 30 commodities into clear, actionable insights for both short-term traders and long-term investors — explore the historic returns major discoveries can generate and begin your 14-day free trial today to position yourself ahead of the broader market.