Great Southern Mining Reports Strong Drilling Results North of Mon Ami Deposit
The Great Southern Mining Mon Ami gold project RC drilling program marks a significant milestone for Great Southern Mining Ltd (ASX: GSN), which has commenced Reverse Circulation (RC) drilling at the Mon Ami Gold Project in Western Australia. The company has described this as its largest drilling campaign since acquiring the Duketon Gold Project tenure in 2021. According to the latest ASX announcement on 24 June 2026, the wider programme totals up to 20,000 metres of RC drilling across Great Southern Mining Ltd's Western Australian portfolio, with activities fully funded and sequenced across three key targets.
The programme begins at Mon Ami, where existing JORC (2012) resources are being tested for extensions, before the RC rig moves on to the Golden Boulder and Amy Clarke discoveries within the Duketon Gold Project.
Mon Ami is located approximately 12 km south of Laverton, WA, on a granted mining licence within the Barnicoat Shear, a regional geological structure that already hosts multiple gold deposits to the north, such as the Barnicoat Mine and Ida H Mine (owned by Genesis Minerals, ASX: GMD).
The project contains a defined JORC (2012) Mineral Resource of 1.56 Mt at 1.11 g/t Au for 55,500 ounces of gold (as reported on 21 July 2021). According to Great Southern Mining Ltd, this resource remains open to the north, northwest and down dip, meaning previous drilling has not closed off mineralisation in those directions.
The current Mon Ami RC programme totals up to 3,000 metres, with two main aims:
The company has estimated the Mon Ami campaign will take around three weeks. On completion, the same RC rig is scheduled to mobilise directly to the Golden Boulder discovery within Great Southern Mining Ltd's 100%-owned Duketon Gold Project.
The ASX announcement confirms that Mon Ami is part of a broader up to 20,000 metre RC drilling programme spanning several Western Australian projects. Furthermore, this is the largest RC campaign undertaken by Great Southern Mining Ltd since it entered the Duketon district.
Drilling has been structured as a pipeline of activity across three main targets:
| Target | Project | Current Status | Next Planned Step |
|---|---|---|---|
| Mon Ami | Mon Ami Gold Project | JORC (2012) Mineral Resource 1.56 Mt @ 1.11 g/t Au for 55.5 Koz | Up to 3,000 m RC currently underway |
| Golden Boulder | Duketon Gold Project | Mineralisation traced over 3.5 km, open along strike and at depth | RC rig to move here after Mon Ami |
| Amy Clarke | Duketon Gold Project | Mineralisation traced over 4.7 km, open along strike and at depth | RC drilling planned following Golden Boulder |
Golden Boulder and Amy Clarke have already shown multi-kilometre strike lengths in earlier drilling and aircore work. According to the company's previous disclosures, both prospects remain open along strike and at depth, indicating that the limits of the mineralised systems have not yet been defined.
Programme scale highlight: The ASX announcement states that the up to 20,000 metre RC programme represents the largest drilling initiative by Great Southern Mining Ltd since the Duketon tenure was acquired in 2021.
Reverse Circulation drilling is one of the most widely used techniques in Australian gold exploration. It is designed to balance cost, speed, and sample quality.
In simple terms:
RC drilling differs from diamond drilling, which retrieves core (solid cylinders of rock). RC produces chips rather than core but is generally:
For projects like Mon Ami, Golden Boulder, and Amy Clarke, where mineralisation has already been identified and needs to be stepped out or extended, RC drilling provides a practical way to:
From an investor perspective, RC drilling often drives the short to medium-term news flow for an exploration company such as Great Southern Mining Ltd. Each RC programme can deliver:
At Mon Ami, RC results have the potential to inform any future update to the 55,500 ounce JORC Mineral Resource, as well as test whether the northern target 250 metres beyond the current resource contains additional zones of gold mineralisation. Consequently, results could also confirm the extent of previous high-grade intercepts at depth.
At Golden Boulder and Amy Clarke, the ASX announcement indicates that RC drilling will focus on large mineralised trends already outlined over 3.5 km and 4.7 km respectively. If these programmes define consistent zones with suitable width and grade, they could support maiden Mineral Resource estimates in due course, subject to sufficient drilling density.
The announcement confirms that Great Southern Mining Ltd is fully funded for all planned drilling activities. The company recently settled the final tranche of a $4.6 million equity placement in early June 2026.
Key programme metrics are summarised below:
| Programme Metric | Detail |
|---|---|
| Total planned RC drilling | Up to 20,000 m |
| Mon Ami component | Up to 3,000 m |
| Subsequent targets | Golden Boulder, then Amy Clarke (Duketon Gold Project) |
| Funding status | Fully funded, $4.6M placement settled June 2026 |
| Scale context | Largest RC drill programme since Duketon acquisition 2021 |
| Mon Ami duration estimate | Approximately 3 weeks |
From an investment point of view, funding certainty reduces the risk that drilling programmes could be delayed or cut back due to capital constraints. In addition, it supports the planned continuous sequence of drilling across the three targets, which can help maintain a stream of technical updates to the market.
The Mon Ami Gold Project lies within trucking distance of multiple operating and emerging gold processing facilities in the Laverton district. According to Great Southern Mining Ltd, all of its Laverton and northern Queensland projects are located within roughly 40 km of operating mills and major operations.
For investors, the location offers two potential advantages if future studies support development:
The Barnicoat Shear, where Mon Ami is located, already hosts multiple gold deposits and operating mines. This provides geological context that the broader corridor has been able to support economic gold projects in the past, although each deposit still requires its own technical and economic assessment.
The commencement of the Great Southern Mining Mon Ami gold project RC drilling program positions the company for an extended period of exploration activity across several established targets in a well-known gold region.
Key elements for investors to monitor include:
Resource growth potential at Mon Ami
Advancement of the Golden Boulder discovery
Scale and continuity at Amy Clarke
Continuous exploration news flow
Key takeaway for investors: Great Southern Mining Ltd is conducting a fully funded, up to 20,000 metre RC drilling programme across three Western Australian gold targets, starting with Mon Ami. The programme focuses on extending an existing JORC Mineral Resource and testing large mineralised trends at Golden Boulder (3.5 km) and Amy Clarke (4.7 km) that remain open along strike and at depth.
According to the ASX announcement and previous reporting (21 July 2021), Mon Ami hosts a JORC (2012) Mineral Resource of 1.56 million tonnes at 1.11 g/t gold for 55,500 ounces of contained gold.
The present RC programme at Mon Ami comprises up to 3,000 metres as part of the broader up to 20,000 metre RC programme across Great Southern Mining Ltd's Western Australian projects.
Once the estimated three-week RC programme at Mon Ami is completed, the drill rig is scheduled to mobilise immediately to the Golden Boulder discovery within the Duketon Gold Project. RC drilling at the Amy Clarke discovery is planned to follow Golden Boulder.
Yes. The company has stated it is fully funded for all planned drilling activities, following settlement of the final tranche of a $4.6 million equity placement in early June 2026.
The Laverton district and Duketon belt are established gold-producing regions in Western Australia, hosting multiple operating mines and processing facilities. Mon Ami sits on the Barnicoat Shear, which also hosts other gold deposits such as Barnicoat and Ida H. This regional context indicates that the area has supported gold mineralisation historically, although each new project must still demonstrate technical and economic viability in its own right.
The Great Southern Mining Mon Ami gold project RC drilling program, alongside the subsequent programmes at Golden Boulder and Amy Clarke, provides a structured, fully funded exploration sequence in a recognised Australian gold district. Investors are consequently likely to focus on the potential for resource growth and the definition of new mineralised zones across these targets as results emerge.
Great Southern Mining Ltd (ASX: GSN) is now drilling across three Western Australian gold targets — Mon Ami, Golden Boulder, and Amy Clarke — in a fully funded, up to 20,000 metre RC programme. With an existing JORC Mineral Resource at Mon Ami and multi-kilometre mineralised trends awaiting testing at its Duketon Gold Project, this is a pivotal period for the company. To learn more about GSN's projects and investment proposition, visit the official website at gsml.com.au.