European Metals Cinovec Lithium Plant Optimisation Targets $54M Annual Savings
European Metals Holdings Ltd (ASX & AIM: EMH) has reported preliminary tunnel kiln testwork results for the Cinovec Lithium Project in the Czech Republic that point to potential European Metals Cinovec tunnel kiln cost savings, specifically a US$112 million reduction in capital expenditure (capex) and US$10 million per annum in operating cost (opex) savings compared with the Definitive Feasibility Study (DFS) rotary kiln design.
When these potential savings are viewed together with the previously announced Lithium Chemical Plant (LCP) flowsheet optimisation, European Metals Holdings Ltd reports a combined possible benefit of ~US$112 million in capex savings and ~US$64 million per year in opex savings. The company notes that the impact of these changes on Cinovec's DFS metrics will only be known once the DFS is updated.
Keith Coughlan, Executive Chairman, European Metals Holdings Ltd, commented:
"The use of a tunnel kiln is a potentially important change from the DFS of the Cinovec Project. If adopted this change could result in a significant reduction in the capex as a result of the use of off-the-shelf components, modular construction as well as considerable opex reductions relating to the reduction in the roasting temperature of the Zinnwaldite concentrate and the option to use electricity instead of gas to fire the kilns. The use of green electricity to fire the kiln could also drastically reduce the carbon footprint of the Project enabling Cinovec to be a leading low carbon producer of Lithium Carbonate."
According to the announcement, a final decision on adopting the tunnel kiln configuration is expected by Q4 2026, after which project company Geomet s.r.o. would update the DFS.
The Cinovec DFS, released in December 2025, describes a pyrometallurgical stage within the LCP that uses two gas-fired rotary kilns to heat zinnwaldite concentrate and roasting reagents to 950°C for one hour, followed by leaching in water at 60°C. Extensive testwork for that study indicated a 93.2% lithium extraction into pregnant leach solution.
European Metals Holdings Ltd is now assessing a change from the DFS configuration of two rotary kilns to a single tunnel kiln. According to the company, the tunnel kiln is expected to:
The company advises that the tunnel kiln option is not expected to affect the overall project timeline, as the tunnel kiln is modular, generally simpler to design and construct, and is typically not a long-lead item.
For investors, the key relevance of the European Metals Cinovec tunnel kiln cost savings lies in:
A rotary kiln is a large, slowly rotating cylindrical furnace. Material moves through the kiln as it rotates and is heated by a single large burner.
In the Cinovec DFS design:
This overshoot can cause vitrification, where material partially melts into a glass-like phase. The announcement explains that this can:
Rotary kiln availability in the DFS is therefore assumed at 85% to accommodate such downtime, and a mill is required after roasting to deal with vitrified material.
A tunnel kiln is a long, stationary furnace. Material is transported through it on cars or conveyors, passing through zones heated by multiple burners or electric elements, with recirculating hot air.
For Cinovec, European Metals Holdings Ltd reports that tunnel kiln operation is expected to involve:
The more precise temperature control is described as:
Furthermore, recent testwork has confirmed that maintaining the solids at 850°C for 30 minutes can achieve the same or slightly higher lithium roast/leach extraction as the DFS rotary kiln conditions of 925°C for one hour.
| Feature | DFS rotary kilns | Proposed tunnel kiln |
|---|---|---|
| Number of units | 2 | 1 |
| Heating mode | Gas-fired | Gas or electric |
| Target solids temperature | 925°C | 850°C |
| Typical gas temperature | >100°C above solids | 870–880°C |
| Residence time at target temp | 60 minutes | 30 minutes confirmed equivalent |
| Lithium recovery (roast/leach) | 93.2% | 93.4% reported |
| Temperature control | 30–50°C overshoot risk | ±10°C |
| Vitrification risk | Present, needs post-roast milling | Designed to avoid vitrification |
| Availability assumption | 85% | High, exact figure not yet disclosed |
| Construction | Elevated, gradient critical | Ground-level, modular |
| Expected capex impact | DFS baseline | ~US$112M reduction (gas-fired vs gas rotary) |
| Expected opex impact | DFS baseline | ~US$10M per year reduction |
These changes directly affect:
European Metals Holdings Ltd, through Geomet s.r.o., has been assessing tunnel kilns for Cinovec since 2022, starting with a scoping-level engineering study. Testwork and design have been led by Dr Jeff Claflin, who previously worked on tunnel kiln designs for the Sonora Project, which were incorporated in that project's DFS.
The first phase focused on confirming that tunnel kiln use for Cinovec zinnwaldite concentrate had no fundamental technical flaws. According to the announcement, this phase:
The second phase aimed to generate engineering design criteria suitable for DFS-level assessment for the Prunéřov plant site. According to European Metals Holdings Ltd, this work included:
Phase 2 testwork outcomes reported in the announcement include:
The capex and opex estimates comparing gas-fired rotary kilns with a gas-fired tunnel kiln are:
European Metals Holdings Ltd has stated that the precise effect on project economics will be quantified through a rigorous DFS update process once a final decision is made.
The tunnel kiln work builds on the LCP flowsheet optimisation reported on 24 June 2026. That earlier optimisation targeted the hydrometallurgical stages of the Lithium Chemical Plant.
The company has presented the combined potential savings as follows:
| Initiative | Capex saving | Opex saving (per year) |
|---|---|---|
| Tunnel kiln (gas-fired vs DFS rotary kilns) | ~US$112M | ~US$10M |
| LCP flowsheet optimisation | Included in combined capex figure | ~US$54M |
| Combined potential saving | ~US$112M | ~US$64M |
Management has noted that these changes, if adopted and confirmed in the updated DFS, have the potential to materially improve project metrics such as NPV8. However, all such outcomes remain subject to formal DFS revision.
For investors, the key point is that European Metals Holdings Ltd is working on both front-end thermal processing efficiency through the tunnel kiln and downstream chemical flowsheet efficiency in the LCP, which together target both capital intensity and operating margin.
Pyrometallurgy refers to processing ore and concentrates using high temperatures to bring about physical and chemical changes. At Cinovec, the pyrometallurgical stage involves:
The goal is to maximise the percentage of lithium that moves from the solid concentrate into the liquid solution for further refining. This percentage is often called roast/leach recovery.
For a lithium project such as Cinovec, kiln performance impacts:
The tunnel kiln approach being evaluated by European Metals Holdings Ltd seeks to balance these factors by running at a lower solids temperature (850°C vs 925°C), achieving precise temperature control (±10°C), avoiding vitrification and related downtime, recovering heat from hot solids to dry and pre-heat reagents, and reducing dust and off-gas volumes, which can decrease gas cleaning requirements.
Consequently, for investors, kiln technology influences the cost per tonne of lithium carbonate, the reliability of production, and potentially the emissions profile of the operation.
European Metals Holdings Ltd notes that the tunnel kiln can be heated by gas or electricity. If electrical heating is used and is supplied by renewable power, testwork suggests:
Geomet's partner, CEZ a.s., is a major Central European energy group with a strategy called Clean Energy for Tomorrow, focused on decarbonisation and the development of renewable and nuclear power sources.
While the announcement does not quantify specific power supply contracts for Cinovec, the ability to operate the tunnel kiln on electricity provides optionality for aligning with lower-emission energy sources in the Czech Republic. This optionality may be relevant for:
The background information in the announcement reiterates key DFS metrics for Cinovec.
| Category | Tonnage (Mt) | Grade Li₂O (%) |
|---|---|---|
| Measured | 54.4 | 0.58 |
| Indicated | 378.23 | 0.41 |
| Inferred | 309.49 | 0.39 |
| Total resource | ~748 | 0.19 Li₂O (average, including lower-grade material) |
A Proven and Probable Ore Reserve of 54.4 Mt at 0.58% Li₂O has been declared, intended to support the first 26 years of mining at an output of 37,500 tpa of lithium carbonate.
The DFS concluded that this supports:
Cinovec is described as the largest hard rock lithium deposit in Europe and the largest such deposit in the European Union.
Key structural and location features include:
The project also benefits from established regional infrastructure, including a sealed road adjacent to the deposit, rail lines 5 km north and 8 km south, an existing 22 kV transmission line to the historic mine, and a location in an active mining region of the Czech Republic.
According to European Metals Holdings Ltd, Cinovec has:
These figures are referenced as background to the project's policy and funding environment, separate from the technical kiln and flowsheet
With a potential US$112 million capex saving and US$64 million per year in combined opex reductions now on the table, European Metals Holdings Ltd (ASX & AIM: EMH) is making significant strides in strengthening the economic case for what is already Europe's largest hard rock lithium deposit. For investors looking to understand the full scope of the Cinovec project — from its DFS metrics and strategic funding position to the latest processing innovations — visit europeanmet.com to explore the investment opportunity in detail.