Temas Resources Advances RCL Stage 2 for Titanium, Vanadium and Iron

Temas Resources (ASX: TIO) has launched Stage 2 of its RCL metallurgical program with SAGA Metals, targeting first high-purity titanium dioxide, vanadium and iron product samples after Stage 1 delivered recoveries of up to 97.4% vanadium — with a C$650,000–C$750,000 mini-pilot contract on the line if Phase 1 succeeds.
By William Hadrian -
  • Stage 2 of the Temas RCL advancement program is now underway, building on Stage 1 recoveries of up to 90.8% titanium, 97.4% vanadium and 91.5% iron from SAGA's Radar Project mineralization.
  • The eight-week program targets first high-purity titanium dioxide, vanadium and iron product samples — the critical bridge between lab validation and commercial product evaluation.
  • Successful Phase 1 completion could trigger a 10-week mini-pilot program worth C$650,000–C$750,000 in revenue for Temas, subject to SAGA approval.
  • RCL has been independently assessed at over 65% lower processing costs than conventional approaches, with a pilot test at Temas' La Blache property already producing 88 kg of 99.8% pure TiO₂ from approximately one tonne of material.
  • SAGA's Radar Project sits less than 20 kilometres from a deep-water port, strengthening the case for on-site downstream product development.
Summarise with AI:

Stage 2 RCL program underway as Temas and SAGA target first titanium, vanadium and iron products

Building directly on Stage 1 validation, Temas Resources (ASX: TIO) and SAGA Metals Corp. (TSXV: SAGA) have commenced Stage 2 of their collaborative Regenerative Chloride Leach (“RCL”) metallurgical program. Stage 1 established that RCL can extract titanium, vanadium and iron from SAGA’s mineralization at recoveries of up to 90.8% titanium, 97.4% vanadium and 91.5% iron, providing the basis for advancement.

Stage 1 Validation Extraction Recoveries

The eight-week Stage 2 program focuses on optimising the RCL flowsheet, generating first high-purity product samples and establishing the engineering criteria needed for pilot-scale testing. SAGA’s Radar Project is located in Labrador, less than 20 kilometres from a deep-water port.

What Stage 2 sets out to deliver

Optimising the leach circuit

Stage 2 begins by comparing two Run-of-Mine (“ROM”) Massive Oxide samples side by side before the best-performing feed material is carried into detailed optimisation. The key RCL operating variables being optimised are:

  • Hydrochloric acid and magnesium chloride concentrations
  • Temperature
  • Oxidation-reduction potential
  • Retention time
  • Solids concentration
  • Particle size

Downstream solvent extraction and first product samples

The optimised leaching program will generate sufficient pregnant leach solution (“PLS”) to run the solvent extraction (“SX”) circuit. The objective is to recover first samples of high-purity titanium dioxide, vanadium and iron, described in the announcement as the bridge between metallurgical testing and commercial product evaluation.

Developing McCabe-Thiele isotherms forms part of establishing preliminary SX operating parameters, with the program also testing extraction, scrubbing and stripping conditions across the downstream circuit.

Stage-gated deliverables — what Phase 1 produces

Phase 1 of Stage 2 is expected to deliver five defined outputs:

  1. Comparative characterisation and leaching results
  2. Optimised RCL leaching and downstream SX conditions
  3. McCabe-Thiele isotherms
  4. Selection of the preferred feed material
  5. A recommendation regarding readiness for mini-pilot testing

These deliverables provide the basis for the Gate 2 decision on whether to advance to a mini-pilot program.

What is RCL and why does it matter for critical minerals?

Regenerative Chloride Leach (“RCL”) is a hydrometallurgical process that extracts critical metals using a regenerative mixed chloride leaching approach, operating at near-ambient temperatures and pressures. Rather than the high-heat, high-acid conditions used in conventional processing routes, RCL regenerates its reagents within the process, which reduces ongoing costs and waste streams.

The cost advantage is independently validated: RCL has been assessed at over 65% lower in processing costs than conventional approaches, based on independent evaluation by the Natural Resources Research Institute at the University of Minnesota and subsequent pilot-scale validation. In practical terms, a pilot test at Temas’ La Blache property produced 88 kg of 99.8% pure TiO₂ from approximately one tonne of material.

For investors, the commercial significance is straightforward. Temas is developing RCL not just for its own projects but as a technology platform available through licensing, strategic partnerships and joint ventures. The SAGA program represents a real-world third-party application of RCL on mineralization controlled by a separate company, and each completed stage strengthens the commercial case for broader deployment.

Clear line of sight to a mini-pilot and beyond

Successful completion of Phase 1 could trigger Phase 2 of the SAGA program: a mini-pilot expected to run over 10 weeks, subject to Phase 1 completion and approval by SAGA. Phase 2 is expected to generate approximately C$650,000–C$750,000 in revenue for Temas, with the final scope and budget to be confirmed on completion of the Phase 1 optimisation work.

Stage 2 has also been designed with future engineering and economic evaluation in mind, targeting the metallurgical data required to support 500–1,000 kg pilot-scale testing and SAGA’s progression toward PEA/PFS-level evaluation.

The table below shows where the SAGA program sits within Temas’ broader RCL commercialisation roadmap:

Development Stage Status
Laboratory Process Development ✔ Completed
Internal Validation (Temas Projects) ✔ Completed
Third-Party Validation (SAGA Metals – Stage 1) ✔ Completed
Detailed Bench Optimisation (SAGA Metals – Stage 2) Underway
Mini-Pilot Demonstration Planned
Pilot Plant Demonstration Planned
Commercial Deployment / Licensing Long-Term Commercial Objective

Tim Fernback, President and CEO of Temas Resources, described the program’s direction:

Tim Fernback, President and CEO, Temas Resources

“Stage 1 showed RCL works on SAGA’s titanium-vanadium-iron mineralization. Stage 2 is where we move from extraction to an optimized process and the first titanium, vanadium and iron products…”

Mike Stier, CEO of SAGA Metals, pointed to the strategic context of SAGA’s location:

Mike Stier, CEO, SAGA Metals

“…With Radar located less than 20 kilometres from a deep-water port, the opportunity to pursue downstream products on site is a compelling part of the story.”

Don’t Miss the Next Critical Minerals Breakthrough

Get FREE breaking ASX news on titanium, vanadium and iron delivered to your inbox within minutes of release, complete with in-depth analysis already done for you. Join 30,000+ subscribers who stay ahead of the market the moment news breaks. Click the “Free Alerts” button at Discovery Alert to start receiving alerts today.


Frequently Asked Questions

What is Regenerative Chloride Leach (RCL) technology and how does it work?

RCL is a hydrometallurgical process that extracts critical metals like titanium, vanadium and iron using a regenerative mixed chloride leaching approach at near-ambient temperatures and pressures, regenerating its reagents within the process to reduce costs and waste — independently assessed at over 65% lower processing costs than conventional methods.

What did Stage 1 of the Temas and SAGA RCL program achieve?

Stage 1 validated that RCL can extract titanium, vanadium and iron from SAGA's Radar Project mineralization at recoveries of up to 90.8% titanium, 97.4% vanadium and 91.5% iron, providing the technical basis for the Stage 2 optimisation program now underway.

What is the potential revenue for Temas Resources from the SAGA mini-pilot program?

If Phase 1 of Stage 2 is successfully completed and approved by SAGA, the subsequent 10-week mini-pilot program is expected to generate approximately C$650,000–C$750,000 in revenue for Temas Resources, with the final scope to be confirmed on Phase 1 completion.

Where is SAGA's Radar Project located and why does the location matter?

SAGA's Radar Project is located in Labrador, Canada, less than 20 kilometres from a deep-water port — a logistical advantage that makes on-site downstream product development commercially viable and strengthens the project's case for future PEA and PFS-level evaluation.

How does the SAGA program fit into Temas Resources' broader RCL commercialisation strategy?

The SAGA program is the first third-party application of Temas' RCL technology on mineralization controlled by a separate company, and forms part of a broader commercialisation roadmap that includes licensing, strategic partnerships and joint ventures — with each completed external validation strengthening the case for wider deployment.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.