Tanami Gold JV Locks in $38M Macmahon Deal to Unlock 400koz at Groundrush

MGX Resources and Tanami Gold's Central Tanami Project Joint Venture has signed a $38 million decline agreement with Macmahon to unlock 400,000+ ounces of Groundrush gold — with portal construction starting September 2026 and a development decision targeted for 2027.
By William Hadrian -
  • The Central Tanami Project Joint Venture (50% MGX, 50% Tanami Gold) has signed a $38 million contract with Macmahon Underground to construct the Groundrush underground decline, with portal works commencing September 2026.
  • The 3.5km decline will reach approximately 350 metres depth over a 14-month construction period, providing underground drilling platforms for around 33,000 metres of resource definition drilling.
  • The primary objective is converting 400,000+ ounces of Inferred Resources to the higher-confidence Indicated category — the geological standard required to support mine design and a credible development decision.
  • The CTPJV's total Mineral Resource stands at 2.8 million ounces at 2.8 g/t Au (JORC 2012), with the Groundrush deposit alone accounting for 1.2 million ounces at 3.3 g/t Au.
  • Resource conversion data from the decline drilling program feeds directly into the joint venture's targeted 2027 development decision for what management describes as a major new gold business in the Northern Territory.
Summarise with AI:

MGX signs $38 million Macmahon decline agreement to unlock Groundrush gold

MGX Resources has secured a major underground development contract at its Northern Territory gold project. The Central Tanami Project Joint Venture (CTPJV) — owned 50% by MGX and 50% by Tanami Gold NL (ASX:TAM) — has signed a $38 million agreement with Macmahon Underground Pty Ltd, a subsidiary of Macmahon Holdings Limited (ASX:MAH), for construction of the Groundrush underground decline. On-surface works are already underway, with portal construction scheduled to commence in September 2026. This marks a key step toward the joint venture’s targeted development decision in 2027.

Inside the Groundrush decline agreement

The contract with Macmahon is valued at approximately $38 million and covers portal and vent establishment plus the initial 3.5km of decline development to a depth of around 350 metres. The construction period is scheduled for 14 months.

The decline will provide underground drilling platforms to enable approximately 33,000 metres of resource definition (infill) drilling to a depth of around 650 metres. The objective is to convert over 400,000 ounces of Inferred Resources to the higher-confidence Indicated category — a requirement for mine design and development. Infill drilling is expected to commence towards the latter stages of the 14-month decline construction period.

Groundrush Underground Decline Profile

Parameter Detail
Contract Value ~$38 million
Contractor Macmahon Underground Pty Ltd (ASX:MAH subsidiary)
Decline Length 3.5km
Target Depth ~350 metres
Construction Period 14 months
Planned Drilling ~33,000 metres
Target Conversion 400,000+ oz Inferred → Indicated

The bigger resource picture at Central Tanami

The CTPJV’s total Mineral Resource Estimate (JORC 2012) stands at 31.0 million tonnes at 2.8 g/t Au for 2.8 million ounces of contained gold. Within this, the Groundrush Gold Deposit accounts for 11.0 million tonnes at 3.3 g/t Au for 1.2 million ounces of contained gold.

This resource estimate was detailed in the company’s “Central Tanami Gold Project Mineral Resource Update” dated 11 November 2025. For you as an investor, this context matters: Groundrush represents the core asset within a multi-million-ounce resource base, and converting Inferred ounces to Indicated status de-risks the path to development by providing the geological confidence required for mine design.

Why resource conversion matters for investors

Under the JORC Code, mineral resources are classified by geological confidence. Inferred Resources represent mineralisation where data spacing and geological understanding are sufficient to estimate tonnage and grade, but not to support detailed mine planning. Indicated Resources carry higher confidence — closer drill spacing and better geological continuity — and are required for mine design and development decisions.

Building a decline provides underground access to drill systematically from platforms at depth, tightening the drill spacing and upgrading the geological confidence. Converting 400,000+ ounces from Inferred to Indicated is what supports a credible development decision in 2027. Without this conversion, the resource remains conceptual rather than mine-ready.

Other activity across the CTPJV site

Beyond the Groundrush decline, the joint venture is advancing several supporting workstreams:

  • Jims Gold Deposit: Resource definition drilling recommenced in June 2026. Jims was previously mined approximately 25 years ago and offers potential as an expanded open-pit ore source to supplement Groundrush mineralisation. The current Mineral Resource Estimate for Jims totals 2.6 million tonnes at 2.7 g/t Au for 220,000 ounces of contained gold.
  • Accommodation camp and utilities: Considerable repairs and improvements are underway to support upcoming activities.
  • Infrastructure clean-up and repair: The site team is working to restore other infrastructure assets necessary for planned operations.
  • Recruitment: Key site and project roles are being filled to support the development timeline.

What comes next

Macmahon is scheduled to mobilise to site in September 2026 for commencement of in-pit portal construction activities. The 14-month decline build will provide access for underground drilling in the latter stages of the construction period. The resource conversion data will feed directly into the targeted 2027 development decision, building momentum toward what management describes as “establishing a major new gold business in the Northern Territory.”

Peter Kerr, MGX Chief Executive Officer

“The commencement of the Groundrush decline represents a key milestone in the CTPJV’s efforts to advance the project to a development decision and ultimate production.”

“We and our joint venture partner, Tanami Gold, look forward to sharing regular updates as we build momentum towards establishing a major new gold business in the Northern Territory.”

Want the Next ASX Gold Breakout in Your Inbox?

Join 30,000+ investors receiving FREE breaking ASX gold news and in-depth analysis delivered within minutes of release. Click the “Free Alerts” button at Discovery Alert to get market-moving announcements the moment they drop—complete with expert coverage you can act on immediately.


Frequently Asked Questions

What is the Groundrush decline agreement signed by MGX Resources and Tanami Gold?

The Central Tanami Project Joint Venture (50% MGX Resources, 50% Tanami Gold) has signed a $38 million contract with Macmahon Underground to construct a 3.5km underground decline at the Groundrush Gold Deposit in the Northern Territory, with portal construction scheduled to begin in September 2026.

Why does converting Inferred Resources to Indicated matter for the Groundrush project?

Under the JORC Code, Inferred Resources lack the geological confidence required for mine design and development decisions — the underground drilling program enabled by the Groundrush decline is specifically designed to convert 400,000+ ounces from Inferred to Indicated status, which is the threshold needed to support a credible 2027 development decision.

What is the total gold resource at the Central Tanami Project?

The CTPJV's total Mineral Resource Estimate (JORC 2012) stands at 31.0 million tonnes at 2.8 g/t Au for 2.8 million ounces of contained gold, with the Groundrush deposit alone accounting for 1.2 million ounces at 3.3 g/t Au.

When will underground drilling begin at Groundrush?

Infill drilling is expected to commence towards the latter stages of the 14-month decline construction period, meaning drilling is likely to begin in late 2027, with Macmahon scheduled to mobilise to site in September 2026.

What other development activity is underway at the Central Tanami Project alongside the Groundrush decline?

The joint venture has also recommenced resource definition drilling at the Jims Gold Deposit (220,000 ounces at 2.7 g/t Au) as of June 2026, while simultaneously undertaking accommodation camp upgrades, infrastructure repairs, and recruitment of key site roles.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.