Rox Resources Hits Every Build Milestone as Youanmi Eyes Mid-2027 First Gold

Rox Resources' Youanmi Gold Mine construction is tracking on schedule for mid-CY2027 first gold, with mining already exceeding DFS targets, long lead equipment in transit, and a 351-room camp at practical completion — here's what investors need to know.
By William Hadrian -
  • All construction and mining activities at Rox Resources' 100%-owned Youanmi Gold Mine remain on schedule for first gold pour in mid-CY2027, with the MD confirming works have accelerated in recent weeks.
  • Mining in August alone delivered 577m of advance across three areas, exceeding the DFS mine plan, with production stoping anticipated to commence in October 2026 following final assay receipt.
  • Critical long lead items — including primary, secondary, and tertiary crushers — are all in transit, with the first Albion tank shipment departed late August and expected in Perth in late September.
  • The 351-room accommodation camp has reached practical completion, with the wastewater treatment facility commissioned at end of August and the dry mess facility now operational.
  • The project carries a 2.2Moz global mineral resource at 5.6g/t and a long-term production aspiration of 150,000 ounces per annum, backed by $350m in secured debt financing and a completed $218m equity raise.
Summarise with AI:

Youanmi Gold Mine construction and mining on schedule for mid-CY2027 first gold

Rox Resources (ASX: RXL) has confirmed that all construction and mining activities at its 100%-owned Youanmi Gold Mine in Western Australia remain on schedule, targeting first gold pour in mid-CY2027. The company is developing a project hosting a global mineral resource of 2.2Moz at 12.1Mt at 5.6g/t, with a long-term aspiration of 150,000 ounces per annum.

Processing plant construction advances across all fronts

Construction of the 1.0Mtpa Youanmi Processing Plant by EPC provider Interquip has made significant progress, with bulk earthworks complete across all sites, infrastructure foundations poured, and structural works underway. Concrete milestones achieved include:

  • Screen plant concreting complete
  • Crusher foundation complete, with primary crusher walls now under construction
  • Fine ore bin tunnel pour complete
  • Ball mill foundation poured
  • ISAMill foundation poured
  • CIL (Carbon-in-Leach) pad complete, with tank construction advancing

Long lead items — the large, specialist pieces of equipment with extended delivery windows — are now in transit or on-site, signalling the construction critical path is intact:

  • First shipment of Albion tanks departed late August, expected in Perth in late September
  • Crushers (primary, secondary, and tertiary) all in transit
  • Ball mill for limestone circuit in Perth
  • Rock breaker in Perth

Remaining long lead items are under construction and remain on schedule for shipping and delivery to site.

Tailings storage facility and camp: both taking shape

The tailings storage facility is progressing, with clearing complete, the cut-off drain largely complete, and test pads finished ahead of construction of the outer dam wall. This supporting infrastructure is a prerequisite for the plant to operate once commissioned.

The 351-room accommodation camp has reached practical completion. The wastewater treatment facility was commissioned at the end of August, and the new dry mess facility is operational, providing kitchen and dining facilities for the planned permanent and construction workforce. September works include refurbishing the existing dry mess into a wet mess facility and installing sports court infrastructure.

Mining exceeds DFS targets as ore stockpile builds

Mining performance at Youanmi is running ahead of the Definitive Feasibility Study (DFS) mine plan. In August alone, 577m of mining was completed, comprising 431m of development advance across three mining areas and 146m of stripping in the historic Youanmi Decline.

At United North, ore drive development is largely complete on the first two levels, extending past the DFS mine plan. The escapeway network has been excavated to 2325mRL via raise bore, servicing the first four planned production levels, with ladderways to be installed in September.

At Youanmi Main, access to the first production levels has commenced from the main decline. The primary pump station installation is nearing completion, which is expected to accelerate dewatering of the historic decline.

Production stoping is anticipated to commence in October, following receipt of final assays and completion of geology grade control model updates. That milestone directly de-risks the ore stockpile build required before processing plant commissioning.

The high-grade underground results confirmed across the United North and Youanmi Main ore bodies gave the grade control team confidence in the geological continuity assumptions that underpin the October stoping schedule.

What is a CIL (Carbon-in-Leach) plant and why it matters for gold investors

A Carbon-in-Leach plant is the processing facility where crushed and ground ore is mixed with a cyanide solution to dissolve the gold. Activated carbon is then added to the slurry to absorb the dissolved gold, which is subsequently stripped from the carbon and refined into gold doré bars ready for sale. It is the standard processing route for high-grade gold projects like Youanmi.

Gold recovery rates at Youanmi have been validated at 94% through the Albion Process testwork, a result that directly supports the revenue assumptions built into the DFS and gives investors confidence that the CIL plant will perform as designed once commissioned.

At a throughput rate of 1.0Mtpa, the Youanmi processing plant is designed to handle one million tonnes of ore per year once operational. The company’s long-term aspiration is to reach 150,000 ounces per annum of gold production.

For investors tracking development-stage gold companies, construction milestones on a CIL plant carry real weight. Foundations, long lead item deliveries, and tank installations are the events where delays most commonly translate into cost overruns and schedule slippage. Each milestone confirmed on schedule reduces the commissioning risk profile of the project.

Pathway to production: milestones met, next steps in focus

Phill Wilding, Managing Director & CEO, Rox Resources

“Construction works have accelerated in recent weeks as we start to transform the Youanmi Gold Mine into a production and processing hub, ahead of first gold pour next year.”

Phill Wilding, Managing Director & CEO, Rox Resources

“This rapidly advancing on-site activity is setting the stage for the Youanmi Gold Mine to progress towards our aspiration of becoming a 150,000ozpa operation in future years.”

The table below summarises completed milestones and the next steps on Rox’s indicative pathway to production, which the company has confirmed remains on track.

Pathway to Production Timeline

Milestone Status Detail Target / Completion Date
Definitive Feasibility Study released Complete DFS published confirming project economics November 2025
$200m Placement + $18m SPP Complete Equity funding component finalised December 2025
$350m Debt Financing secured Complete Debt facility secured to fund construction March 2026
MDCP approval received Complete Approval for processing plant, tailings, and associated site infrastructure March 2026
Final Investment Decision (FID) Complete Board approved FID to proceed with development March 2026
Works Approval received Complete Regulatory works approval granted July 2026
Dewatering at Main Pit completed Complete Transitioned to underground dewatering Completed
351-room accommodation camp Complete Practical completion achieved; wastewater treatment commissioned end of August August 2026
Oxygen Supply contract In Progress Preferred supplier selected; early works agreement in place Ongoing
Debt Facility drawdown conditions precedent In Progress All conditions precedent to be satisfied Ongoing
Production stoping commencement Upcoming Anticipated following receipt of final assays and grade control model updates October 2026 (anticipated)
Ore stockpile build Ongoing Continued development from all declines targeting commissioning stockpile Ongoing
First gold pour Target Processing plant commissioning and first production Mid-CY2027 (target)

Remaining next steps include finalising the Oxygen Supply contract, continuing underground development across all declines, building the ore stockpile, and continuing to define near-mine and regional exploration targets.

With mining already exceeding DFS advance rates, construction milestones ticking over on schedule, and long lead items either on-site or in transit, Rox’s development programme is progressing with the operational discipline that matters most at this stage: keeping the critical path intact ahead of the commissioning window.

Don’t Miss the Next ASX Gold Producer

Get breaking ASX gold news delivered to your inbox within minutes of release, complete with in-depth analysis already done for you. Join 30,000+ investors who rely on Big News Blast for FREE real-time alerts the moment market-moving announcements hit. Click the “Free Alerts” button to stay ahead of the market on ASX gold and mining news.


Frequently Asked Questions

When is Rox Resources' Youanmi Gold Mine expected to pour first gold?

Rox Resources is targeting first gold pour at the Youanmi Gold Mine in mid-CY2027, with the company confirming in September 2026 that all construction and mining activities remain on schedule to meet that target.

What is the Youanmi Gold Mine's mineral resource and production target?

The Youanmi Gold Mine hosts a global mineral resource of 2.2 million ounces at 12.1Mt at 5.6g/t, with Rox Resources holding a long-term aspiration of reaching 150,000 ounces of gold production per annum.

What is a Carbon-in-Leach (CIL) plant and how does it work in gold processing?

A Carbon-in-Leach plant processes crushed ore by mixing it with a cyanide solution to dissolve gold, then uses activated carbon to absorb the dissolved gold, which is subsequently stripped and refined into gold doré bars ready for sale — it is the standard processing route for high-grade gold projects like Youanmi.

How is mining at Youanmi tracking against the DFS mine plan?

Mining at Youanmi is running ahead of the Definitive Feasibility Study mine plan, with 577m of mining completed in August 2026 alone across three mining areas, and ore drive development at United North already extending past the DFS plan on the first two levels.

How is the Youanmi Gold Mine construction being funded?

Construction is funded through a combination of a $350 million secured debt facility finalised in March 2026 and a $218 million equity raise comprising a $200 million placement and an $18 million Share Purchase Plan completed in December 2025.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.