Rox Resources Hits 12.10m at 13.36g/t Gold as United North Stope Planning Starts

Rox Resources has started stope planning as United North production edges closer, backed by a 12.10m at 13.36g/t Au intercept and levels running 125m beyond the DFS mine plan.
By William Hadrian -
  • Rox Resources has completed preparation works for production stoping at United North and started stope planning on the 2356 and 2341mRL levels.
  • Hole UNN26_038 returned 12.10m at 13.36g/t Au from 136.82m, including 7.53m at 20.86g/t Au, with host shear zones seen in every hole.
  • The first two levels extend about 125m beyond the DFS mine plan, giving scope to run production ahead of the DFS schedule.
  • The top six levels are drilled enough to support production planning, and the next four are infilled to 20m x 20m, with a 12-month drilling lead targeted by mid-CY2027.
  • Northern ore drive assays and surface growth drilling results are still to come, and the 150,000ozpa goal is an aspiration with no production or funding figures behind it.
Summarise with AI:

Stope planning underway at United North as infill drilling returns high-grade gold

Rox Resources (ASX: RXL) has commenced stope planning for the 2356 and 2341mRL levels at United North, with preparation works for production stoping now complete. The company also reported high-grade gold drilling results, led by 12.10m @ 13.36g/t Au from 136.82m (UNN26_038), including 7.53m @ 20.86g/t Au.

United North is part of the 100%-owned Youanmi Gold Mine in Western Australia. A stope is the underground void left once ore is mined out, so stope planning is the step where designs are drawn up for extraction.

For investors, the announcement points to a company moving from development towards production. The drilling is aimed at giving that move firmer geological footing.

Phill Wilding, Managing Director & CEO

“Preparation works for production stoping at United North are now complete, with the mining team progressing stope designs ahead of extraction. This marks an important milestone as we transition from development towards production at the high-grade United North area…”

Thick, high-grade intercepts across United North

Underground diamond drilling at United North continues to return thick, high-grade gold intersections. Host shear zones were observed in all drill holes.

Headline drill results

The table below sets out the significant results reported. Grades are in grams per tonne of gold (g/t Au), and all widths are downhole widths.

Hole ID Interval Grade (g/t Au) From (m) Including
UNN26_024 7.54m 11.95 155.51 2.70m @ 23.60g/t Au from 156.70m
UNN26_031 22.34m 3.37 170.00 3.30m @ 7.87g/t Au from 188.60m
UNN26_036 6.89m 10.36 140.26 4.97m @ 12.34g/t Au from 140.26m
UNN26_038 12.10m 13.36 136.82 7.53m @ 20.86g/t Au from 140.02m
UNN26_040 8.05m 6.18 163.51 2.60m @ 12.58g/t Au from 164.12m
UNN26_021 19.77m 2.49 108.40 6.91m @ 2.29g/t Au from 108.40m, and 6.26m @ 4.24g/t Au from 121.91m

Thickness and grade together matter here. A wide intercept at a high grade, such as UNN26_038, carries far more gold per drill hole than a narrow one.

Diamond drilling remains on schedule, with 16 holes totalling 3,091.7m completed during September.

Why the consistency matters

Mr Wilding said the consistency of mineralisation continues to stand out. He said the company is seeing thick intercepts and high grades throughout the drilling.

The company says the results support confidence in the delivery of high-grade ounces from the Youanmi ore system. It also says they further support the initial production stopes within the Definitive Feasibility Study (DFS) mine plan.

Levels extend ~125m beyond the DFS mine plan

Final assays have been received and grade control modelling and estimation completed for the 2356 and 2341mRL levels. The results continue to confirm strike extensions of approximately 125m beyond the levels originally designed in the DFS.

The grade control model indicates additional mineralisation compared with the DFS mine plan. According to the company, this provides scope to maintain production at a rate ahead of the schedule contemplated in the DFS.

Phill Wilding, Managing Director & CEO

“The first two development levels have already extended approximately 125 metres each beyond the original DFS mine plan, providing access to additional high-grade mineralisation and supporting the potential for increased production from these levels.”

Progress across the upper levels of United North is as follows:

  • The top six levels are now sufficiently drilled to support production planning and mine development
  • The next four southern ore drive levels (2325, 2310, 2290 and 2285mRL) are now infilled to a nominal 20m x 20m spacing
  • Ore interpretation and grade control modelling are underway for these four levels
  • Assays remain outstanding for the northern ore drives, where drilling continues to infill to a nominal 20m x 20m spacing

Planning for first production stopes on the top two levels is progressing ahead of the original DFS mine plan.

United North Underground Development Status Diagram

Readers interested in how these production plans translate into returns can see our full explainer on the Youanmi project economics, which sets out the Definitive Feasibility Study assumptions that the United North mine plan is measured against.

What is grade control drilling and why does it matter?

Grade control drilling is infill drilling at close spacing, here a nominal 20m x 20m. It refines where ore sits before mining begins.

For investors, the value is in certainty. Tighter drilling gives a clearer picture of the orebody, which supports mine scheduling and more consistent ore delivery to the mill, according to the company.

The stated aim is that by mid-CY2027, United North is sufficiently infill drilled to maintain a 12-month drilling lead ahead of mining. The company says this will provide greater certainty around future mine production and scheduling.

Next steps and the 150,000ozpa aspiration

Updated estimates for the next four levels are expected to further inform stope planning and production scheduling. Assay results for the northern ore drives are still to come.

Growth drilling from surface is advancing, with results to come. The announcement gives no timing for those results.

Management’s longer-term aspiration is to build Youanmi into a 150,000ozpa operation. That is an aspiration rather than a forecast, and the announcement provides no production or funding figures to support it.

For context, the Youanmi Gold Project hosts a global mineral resource of 12.4Mt at 5.5g/t for 2.2Moz of gold.

The latest results follow releases on 16 July, 17 August and 14 September 2026, which the company says the new results are consistent with in demonstrating the continuity, thickness and grade of mineralisation.

Don’t Miss the Next ASX Gold Breakout

Get FREE ASX gold news delivered to your inbox within minutes of release, with in-depth analysis and the full announcement included. Join 30,000+ investors already receiving real-time alerts from Big News Blast. Click the “Free Alerts” button to stay ahead of the market the moment news breaks.


Frequently Asked Questions

What is a stope in underground gold mining?

A stope is the underground void left once ore is mined out, so stope planning is the stage where designs are drawn up for extraction.

What is grade control drilling and why does it matter?

Grade control drilling is close-spaced infill drilling, here a nominal 20m x 20m, that refines where ore sits before mining begins. It gives a clearer picture of the orebody, supporting mine scheduling and more consistent ore delivery to the mill.

What were the best drill results at Rox Resources' United North?

The headline result was 12.10m at 13.36g/t Au from 136.82m in hole UNN26_038, including 7.53m at 20.86g/t Au. Other holes returned 7.54m at 11.95g/t and 6.89m at 10.36g/t.

When will Rox Resources start production at United North?

The announcement gives no production start date, but stope planning has begun on the 2356 and 2341mRL levels and preparation works for production stoping are complete. Planning for first production stopes on the top two levels is ahead of the original DFS mine plan.

How big is the Youanmi Gold Project resource?

The Youanmi Gold Project hosts a global mineral resource of 12.4Mt at 5.5g/t for 2.2Moz of gold. Management's longer-term aspiration is a 150,000ozpa operation.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.

About the Publisher