Macmahon Locks in $38M Decline Contract to Unlock 400Koz Gold at Groundrush

MGX Resources has signed a $38 million underground decline construction agreement with Macmahon Underground to advance the Groundrush Gold Deposit toward a 2027 development decision — converting 400,000+ ounces of Inferred Resources to Indicated through 33,000 metres of underground drilling.
By William Hadrian -
  • MGX Resources has executed a $38 million contract with Macmahon Underground (ASX: MAH) to construct a 3.5km underground decline at the Groundrush Gold Deposit, with Macmahon mobilising in September 2026.
  • The 14-month decline program targets approximately 33,000 metres of resource definition drilling to convert 400,000+ ounces from Inferred to Indicated classification — the confidence level required for mine design and project financing.
  • The Groundrush deposit hosts 11.0 Mt at 3.3 g/t Au for 1.2 Moz gold, sitting within a broader CTPJV Mineral Resource of 2.8 Moz at 2.8 g/t Au across 31.0 Mt.
  • Surface preparation works are already underway, with laydown areas operational and pit access ramp re-establishment progressing — the project is moving, not waiting.
  • The CTPJV is targeting a formal development decision in 2027, with the Macmahon agreement representing a contracted, scoped, and funded step on that pathway.
Summarise with AI:

MGX Resources has signed a $38 million underground decline construction agreement with Macmahon Underground, advancing the Central Tanami Project Joint Venture (CTPJV) toward a development decision in 2027. The contract, executed between CTP JV Pty Ltd (the CTPJV management entity) and Macmahon Underground Pty Ltd (a subsidiary of Macmahon Holdings Limited, ASX:MAH), marks a concrete step in converting the Groundrush Gold Deposit from an exploration asset into a production-ready mine.

What the $38 million decline delivers

The agreement covers construction of a 3.5km underground decline extending to a depth of approximately 350 metres over a 14-month period. Scope includes portal and vent establishment, with surface preparation works already underway — laydown areas are operational and pit access ramp re-establishment is progressing. Macmahon mobilises in September to begin in-pit portal construction.

The strategic purpose of the decline is to provide underground drilling platforms that enable approximately 33,000 metres of resource definition and infill drilling. The program targets the Groundrush deposit to a depth of around 650 metres, with drilling expected to commence toward the end of the construction period. The key objective: convert over 400,000 ounces of Inferred Resources to the higher-confidence Indicated category required for mine design and development.

Groundrush Decline Cross-Section Schematic

Component Detail
Decline length 3.5km
Depth ~350 metres
Construction period 14 months
Contract value ~$38 million
Drilling program ~33,000 metres
Resource conversion target 400,000+ oz Inferred → Indicated

Why resource conversion matters for investors

Under the JORC (Joint Ore Reserves Committee) classification system, mineral resources sit on a confidence spectrum. Inferred Resources represent the lowest level of geological confidence — you know mineralisation exists, but the data density is insufficient for detailed mine planning. Indicated Resources carry materially higher confidence, backed by enough drilling to support mine design, feasibility studies, and ultimately a development decision.

Converting ounces from Inferred to Indicated is not administrative. It is the pathway to production. You cannot build a bankable feasibility study or secure project financing on Inferred Resources alone. The 400,000+ ounce conversion target at Groundrush directly de-risks the timeline to a 2027 development decision and positions the CTPJV to establish a new Northern Territory gold business.

An underground decline is the vehicle for this conversion because it provides drilling platforms close to the target mineralisation. Surface drilling becomes prohibitively expensive and technically constrained at depth. Underground platforms allow you to drill the deposit systematically, tighten the spacing, and build the geological confidence required to move ounces up the classification ladder.

Context the scale:

  • CTPJV total Mineral Resource (JORC 2012): 31.0 Mt at 2.8 g/t Au for 2.8 Moz contained gold.
  • Groundrush Gold Deposit: 11.0 Mt at 3.3 g/t Au for 1.2 Moz gold.
  • Source: MRE per ASX release “Central Tanami Gold Project Mineral Resource Update” dated 11 November 2025.

Progress across the broader Central Tanami site

Momentum is building across multiple fronts. Resource definition drilling recommenced in June at the Jims Gold Deposit, which was previously mined 25 years ago and offers potential as an expanded open pit ore source to supplement Groundrush feed. Jims currently holds a Mineral Resource Estimate of 2.6 Mt at 2.7 g/t Au for 220,000 oz contained gold.

Parallel to drilling and decline works, the site team is advancing repairs and improvements to the accommodation camp, utilities infrastructure, and other site assets. Key site and project roles are being recruited to support the ramp-up in activity.

Peter Kerr, Chief Executive Officer

“The commencement of the Groundrush decline represents a key milestone in the CTPJV’s efforts to advance the project to a development decision and ultimate production. We and our joint venture partner, Tanami Gold, look forward to sharing regular updates as we build momentum towards establishing a major new gold business in the Northern Territory.”

The road to a 2027 development decision

What happens next follows a methodical sequence:

  1. September — Macmahon mobilises; in-pit portal construction begins.
  2. Over 14 months — Decline development to 3.5km / ~350m depth.
  3. Latter stages — Underground drilling platforms established; ~33,000m infill drilling commences.
  4. Target — Convert 400,000+ oz to Indicated to support a development decision in 2027.

The investment thesis is straightforward. The CTPJV is executing a funded, staged plan to de-risk Groundrush and advance it toward production. The Macmahon agreement is not speculative. It is contracted, scoped, and on the ground. Each metre of decline extends the drilling reach. Each drill hole converts Inferred ounces to Indicated. Each converted ounce tightens the pathway to a development decision and a potential major new Northern Territory gold business.

Get ASX Gold News Before the Market Moves

Join 30,000+ investors receiving FREE breaking ASX gold alerts delivered within minutes of release, complete with in-depth analysis. Click the “Free Alerts” button at Big News Blast to start receiving real-time updates the moment market-moving announcements hit the ASX.


Frequently Asked Questions

What is the Macmahon Groundrush decline agreement?

It is a $38 million underground decline construction contract between CTP JV Pty Ltd (the Central Tanami Project Joint Venture management entity) and Macmahon Underground Pty Ltd, covering the construction of a 3.5km decline to approximately 350 metres depth over 14 months at the Groundrush Gold Deposit in the Northern Territory.

Why does MGX Resources need an underground decline at Groundrush?

The decline provides underground drilling platforms that allow approximately 33,000 metres of infill drilling to convert 400,000+ ounces of Inferred Resources to the higher-confidence Indicated category — a prerequisite for mine design, feasibility studies, and securing project financing ahead of a targeted 2027 development decision.

What is the difference between Inferred and Indicated mineral resources?

Under the JORC classification system, Inferred Resources have the lowest geological confidence and cannot support mine design or project financing, while Indicated Resources carry materially higher confidence backed by sufficient drilling density to underpin feasibility studies and development decisions.

When does Macmahon start construction on the Groundrush decline?

Macmahon is scheduled to mobilise in September 2026 to begin in-pit portal construction, with surface preparation works including laydown areas and pit access ramp re-establishment already underway.

How large is the Central Tanami Project's total gold resource?

The CTPJV holds a total Mineral Resource of 31.0 Mt at 2.8 g/t Au for 2.8 Moz of contained gold under JORC 2012, with the Groundrush Gold Deposit alone accounting for 11.0 Mt at 3.3 g/t Au for 1.2 Moz.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.