  • Avenira has started a PQ3 sampling program at its 100%-owned Wonarah Phosphate Project to support commercial specifications and pricing under the Hebang offtake.
  • The Hebang agreement covers up to 500,000 tonnes per annum over four years, approximately 83% of forecast annual DSO production.
  • Sample deliveries to other prospective customers are due to start this quarter, a direct step toward reducing reliance on a single buyer.
  • Sampling drilling is set to finish before 30 November, with pre-strip targeted for Q4 CY2026 and first DSO shipment for H1 CY2027.
  • Management says the program does not alter the Wonarah development timetable, and site mobilisation and logistics preparation are progressing in parallel.
Summarise with AI:

Wonarah sampling program commenced to support offtake and customer engagement

Avenira (ASX: AEV) has commenced an additional product qualification sampling program at its 100%-owned Wonarah Phosphate Project in the Northern Territory. The program is designed to support commercial specification and pricing under the existing Hebang offtake agreement, and to engage with other prospective customers.

The company stated the program continues its commercialisation activities and does not alter the existing development timetable for Wonarah.

For you as an investor, the point is simple. The work moves Wonarah from a resource towards commercial supply, and it signals Avenira is building customer interest beyond a single buyer.

John He, Chief Executive Officer (CEO)

“Wonarah is one of Australia’s largest undeveloped phosphate deposits…”

Hebang offtake and broader customer pipeline

Four-year Hebang agreement

The sampling supports Avenira’s recently announced offtake agreement with Sichuan Hebang Biotechnology Co., Ltd. (“Hebang”). The key terms are:

  • Counterparty: Sichuan Hebang Biotechnology Co., Ltd.
  • Term: four years
  • Volume: up to 500,000 tonnes per annum of phosphate rock from Wonarah
  • Share: approximately 83% of forecast annual direct shipping ore (DSO) production

Previous testing has established the suitability of Wonarah phosphate rock for Hebang’s downstream processing. Further bulk-sample or industrial-furnace trials contemplated under the agreement will support finalisation of commercial product specifications and associated quality and pricing parameters ahead of commercial supply.

Flexibility beyond Hebang

Avenira retains flexibility to pursue customers and pricing opportunities outside the Hebang arrangement. Sample deliveries to other prospective customers are expected to commence this quarter, as part of a broader strategy to build a diversified customer base for Wonarah phosphate products as production ramps up.

That matters because Hebang represents roughly 83% of forecast DSO output. Additional customers would reduce reliance on a single buyer.

Direct shipping ore explained and the road to first shipment

What is DSO and why sampling matters

Direct shipping ore (DSO) is material that is mined and shipped with minimal processing. Buyers typically need representative samples to confirm quality before commercial specifications and pricing are settled.

That explains the fresh drilling. The material previously extracted from the Wonarah trial pit has been substantially utilised for product testing, marketing activities and offtake discussions, so the program uses PQ3 drilling to generate additional representative phosphate material for product qualification, industrial trials and customer engagement.

Timeline to production

The announcement sets out the following milestones. The drilling completion date is stated in the source without a year.

Milestone Timing Status
Sampling drilling completes Before 30 November Underway
Sample deliveries to other prospective customers Expected to commence this quarter Planned
Pre-strip activities Q4 CY2026 Targeted
First DSO shipment H1 CY2027 Targeted

Project development activities are progressing in parallel, including site mobilisation for pre-strip and logistics preparation.

Wonarah Project DSO Development Timeline

Next on the watch list are the sample deliveries, finalised product specifications and pricing parameters, and the commencement of pre-strip activities.

Don’t Miss the Next ASX Phosphate Breakout

Get FREE breaking ASX mining news delivered to your inbox within minutes of release, complete with in-depth analysis. Join 30,000+ investors already staying ahead of the market. Click the “Free Alerts” button at Big News Blast to receive market-moving announcements the moment they break.


Frequently Asked Questions

What is direct shipping ore (DSO)?

Direct shipping ore is material that is mined and shipped with minimal processing. Buyers typically need representative samples to confirm quality before commercial specifications and pricing are settled.

What is the Avenira Wonarah Phosphate sampling program for?

The program uses PQ3 drilling to generate fresh representative phosphate material for product qualification, industrial trials and customer engagement. It supports commercial specification and pricing under the Hebang offtake agreement and talks with other prospective customers.

What are the terms of Avenira's Hebang offtake agreement?

The agreement with Sichuan Hebang Biotechnology runs for four years and covers up to 500,000 tonnes per annum of phosphate rock from Wonarah. That is approximately 83% of forecast annual DSO production.

When is the first Wonarah phosphate shipment expected?

Avenira is targeting pre-strip activities in Q4 CY2026 and the first DSO shipment in H1 CY2027. The company says the sampling program does not change this timetable.

When will Avenira send samples to other potential phosphate customers?

Sample deliveries to other prospective customers are expected to start this quarter. The aim is to build a diversified customer base as production ramps up.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.

About the Publisher