Red Sky Energy Spuds Yarrow 4 in Santos JV as Cooper Basin Production Expands

Red Sky Energy has spudded Yarrow 4 — the first of two back-to-back development wells in the Santos-operated Innamincka Dome JV — marking a key production growth milestone for the ASX junior holding a 20% working interest in the proven Cooper Basin field.
By William Hadrian -
  • Rig 184 spudded Yarrow 4 on 31 August 2026 within PRL 17, kicking off a two-well development program expected to take approximately 10 days per well.
  • Yarrow 5 will be drilled immediately after from the same dual-well pad, compressing the timeline and reducing mobilisation costs across the program.
  • Both new wells tie into Santos's existing Moomba-connected infrastructure, eliminating the need for standalone gathering or processing facilities and accelerating time to first production.
  • Red Sky holds a 20% working interest across six PRLs in the Innamincka Dome JV, with Yarrow 1 and Yarrow 3 already producing gas and liquids into the Santos-operated gathering system.
  • Wet weather delays across the Cooper Basin during the first half of 2026 pushed the program back, making the spud date a material operational milestone for the company.
Summarise with AI:

Red Sky Energy has commenced drilling at Yarrow 4, the first well in a two-well development program within the Santos-operated Innamincka Dome Joint Venture. Rig 184 spudded the well early Monday 31 August 2026 within PRL 17, with drilling expected to take approximately 10 days subject to operational conditions. Red Sky holds a 20% working interest, with Santos (ASX:STO) as operator. Yarrow 5 will follow immediately from the same dual-well pad.

The Yarrow development program explained

This is development drilling within an already-producing field, which means geological risk sits lower than exploration activity. The program follows Red Sky’s execution of a binding Authority for Expenditure (AFE) with Santos in April 2026, advancing activity within the Yarrow field after the tie-in and commissioning of Yarrow 1 in November 2025. Yarrow 1 and Yarrow 3 are currently producing gas and liquids into the Santos-operated gathering system, establishing a production base that the new wells will extend.

The two-well sequence runs as follows:

  1. Yarrow 4 spudded 31 August 2026 (~10 days drilling)
  2. Yarrow 5 to follow immediately from the same dual-well pad
  3. Both wells tie into existing Santos infrastructure, reducing development costs and time to first production

Yarrow Field Development Timeline

The program targets near-term production growth within a proven producing field rather than testing untested geology. That shifts the risk profile materially compared to exploration drilling.

Why the Innamincka Dome matters for investors

The Innamincka Dome is a proven producing region of the Cooper Basin where established infrastructure drives economics. Red Sky holds a 20% working interest across six PRLs (14, 17, 18, 180, 181 and 182) within the Santos-operated Innamincka Dome Joint Venture. Santos operates established gas-gathering, pipeline, and processing infrastructure that connects directly to the Moomba facility.

What that means for you: existing infrastructure reduces per-well development costs and compresses time between drilling completion and first gas. New wells do not require standalone gathering systems, pipelines, or processing facilities — they tie into an operational network. This lowers the capital hurdle and accelerates payback periods relative to greenfield developments.

The table below summarises Red Sky’s position within the Innamincka Dome:

Item Detail
Working interest 20%
PRLs held 14, 17, 18, 180, 181, 182
Operator Santos (ASX:STO)
Producing wells Yarrow 1, Yarrow 3
Infrastructure link Moomba facility

Red Sky participates in development activity within a producing asset base, operated by a major with established infrastructure. That combination de-risks execution relative to early-stage exploration or remote field developments.

Management commentary

The milestone follows wet weather delays that affected drilling schedules across the Cooper Basin during the first half of 2026.

Andrew Knox, Managing Director

“Spudding Yarrow 4 is a key milestone after the wet weather delays across the Cooper Basin. With Yarrow 5 to follow from the same pad, we look forward to Santos progressing the program and will keep the market informed of any significant events.”

What comes next

Immediate next steps centre on drilling execution and operational updates:

  • Yarrow 4 drilling expected to take approximately 10 days from 31 August 2026 spud date
  • Yarrow 5 scheduled to be drilled immediately after from the same dual-well pad
  • Red Sky to update the market on significant events and operational milestones as they are reached

All dates are Santos estimates only, subject to change depending on weather conditions, access windows, and operational scheduling. The company has not disclosed flow rates, reserve figures, or first-production dates for either well. What you are tracking here is drilling execution within a producing field — results and commercial assessment follow post-completion.

Get ASX Oil & Gas News Before the Market Moves

Join 30,000+ investors receiving FREE breaking ASX energy news delivered within minutes of release, complete with in-depth analysis. Click the “Free Alerts” button at Discovery Alert to start receiving real-time alerts on ASX oil and gas developments the moment they break.


Frequently Asked Questions

What is the Yarrow 4 well and why is Red Sky Energy drilling it?

Yarrow 4 is the first of two development wells being drilled by Red Sky Energy within the Santos-operated Innamincka Dome Joint Venture in the Cooper Basin, targeting near-term production growth in a proven field where Yarrow 1 and Yarrow 3 are already producing gas and liquids.

What working interest does Red Sky Energy hold in the Innamincka Dome Joint Venture?

Red Sky Energy holds a 20% working interest across six petroleum retention licences — PRLs 14, 17, 18, 180, 181, and 182 — within the Santos-operated Innamincka Dome Joint Venture in the Cooper Basin.

How long will it take to drill Yarrow 4 and when will Yarrow 5 be drilled?

Yarrow 4 is expected to take approximately 10 days to drill from its 31 August 2026 spud date, with Yarrow 5 scheduled to follow immediately after from the same dual-well pad, subject to operational conditions.

Why does existing Santos infrastructure matter for the Yarrow development program?

Both Yarrow 4 and Yarrow 5 will tie into Santos's existing gas-gathering, pipeline, and processing infrastructure connected to the Moomba facility, which eliminates the need for standalone development infrastructure and reduces both capital costs and the time between drilling completion and first production.

What are the next milestones investors should watch for after the Yarrow 4 spud?

Investors should watch for operational updates as Yarrow 4 drilling completes over approximately 10 days, followed by the commencement and completion of Yarrow 5, with Red Sky committing to update the market on significant events and milestones as they are reached — including any flow rate or production data post-completion.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article