D3 Energy Confirms Gas Zones at Nooitgedacht With Remedial Works to Unlock Flow

D3 Energy's Nooitgedacht drilling update confirms gas-bearing zones in both NGT245 D and NGT245 E wells, with remedial cementing planned to isolate water intrusion and restore flow at the company's 100%-owned ER315 permit in South Africa.
By William Hadrian -
  • Gas-bearing zones have been confirmed in both NGT245 D and NGT245 E wells at Nooitgedacht, with downhole camera footage providing visual evidence of gas bubbling through the water column in NGT245 E.
  • Water incursion from a deeper production zone — not an absence of gas — is identified as the primary cause of suppressed flow, with extremely low reservoir pressure as a contributing factor.
  • Remedial cementing to isolate the deeper water zone is planned to commence the week following the 9 September 2026 announcement, with restoration of drilling-phase flow rates anticipated on success.
  • Nooitgedacht is D3 Energy's first drilling operation at this location, situated approximately 40km from the company's core Production Right application area within the 100%-owned ER315 permit.
  • D3 Energy's flagship PR016 Production Right Application, covering 15% of ER315 and around 9% of its 479,409-acre total land position, remains under assessment by South Africa's Petroleum Agency SA independent of this result.
Summarise with AI:

Drilling confirms gas at Nooitgedacht — remedial works planned to restore flow

D3 Energy (ASX: D3E) has confirmed gas-bearing zones in both the NGT245 D and NGT245 E wells at its Nooitgedacht project, within the 100%-owned ER315 permit in South Africa’s Free State Province. Geophysical logging analysis identified a deeper water production zone in both wells, with water rising above the gas-bearing zones and, due to extremely low reservoir pressure, inhibiting gas flow.

Remedial cementing activities are now being planned to isolate the deeper water zones and restore gas flow to levels observed during drilling. Works are expected to commence the following week on both wells. The Nooitgedacht project represents the company’s first drilling operation at this location, which sits approximately 40km from D3 Energy’s Production Right application area.

What the logging revealed

Prior to water levels rising and inhibiting flow, latest-technology downhole camera logging was able to identify the gas zones. Camera footage confirmed gas bubbling through the water column in NGT245 E — visual evidence that gas-bearing zones are present even as water has temporarily suppressed their output.

Both wells are targeting faulting and associated fractures in the Ventersdorp and Witwatersrand formations to assess reservoir deliverability and collect data on helium and methane concentrations. Key technical findings from the logging analysis include:

  • Deeper water production zone identified in both NGT245 D and NGT245 E
  • Water level now above the gas-producing zones in both wells
  • Extremely low reservoir pressure identified as a contributing factor to inhibited flow
  • Gas bubbling confirmed via downhole camera logging prior to water rising

David Casey, Managing Director and CEO, D3 Energy

“Notwithstanding that gas was encountered during drilling, unsurprisingly given the extremely low reservoir pressure here, gas flow subsided during completion operations. Encouragingly, however, logging has confirmed that this is in large part due to water rising from a zone below to above the gas bearing zone. Downhole camera vision clearly confirms this with gas seen bubbling through the water column. While it is anticipated that remedial work should resolve this, it is nonetheless incredibly encouraging that both wells intersected gas bearing zones in what is our first drilling operation at Nooitgedacht, which is located some 40km from our Production Right application area.”

What is remedial cementing and why does it matter?

Remedial cementing is a standard oil and gas industry technique used to isolate unwanted fluid zones within a wellbore from the zones that are intended to produce. In this case, the goal is to seal off the deeper water production zone so that water can no longer migrate upward into the gas-bearing intervals.

Subsurface Wellbore Challenge and Remedial Cementing Solution

Water incursion into gas wells is a recognised challenge, particularly in low-pressure reservoirs where there is insufficient natural energy to push water back down and maintain gas flow to surface. When reservoir pressure is extremely low, even modest water ingress can overwhelm the gas column and effectively shut in production.

For D3 Energy, a successful cementing operation would confirm that the NGT245 D and NGT245 E wells are capable of producing gas at the rates observed during drilling. The technique addresses a well-construction issue rather than a geological one, which is why the confirmed presence of gas-bearing zones in both wells is the more material finding from this update.

Broader asset context and what comes next

D3 Energy holds a 479,409-acre land position across South Africa’s Free State Province, comprising ER315, PR016, Exploration Right Applications ER386, ER391, ER392 and ER393, and Technical Cooperation Permit TCP273. The company’s flagship ER315 permit has delivered independently verified helium concentrations of up to 8% and is the subject of a Production Right Application (PR016) currently under assessment by South Africa’s Petroleum Agency SA (PASA).

The initial Production Right Application area covers 15% of ER315 and approximately 9% of D3’s total exploration right acreage. ER386 is contiguous with ER315 and sits within the same Virginia Fault structural corridor that hosts D3’s certified reserves and contingent resources. The Nooitgedacht result adds a new data point to the broader appraisal picture, with the project located approximately 40km from the Production Right application area.

D3 Energy recently certified a maiden helium resource at ER386, the permit contiguous with ER315 that sits within the same Virginia Fault structural corridor underpinning the company’s certified reserves and contingent resources.

Key milestones from this point forward include:

  1. Remedial cementing to commence on NGT245 D and NGT245 E — expected the week following the 9 September 2026 announcement
  2. Restoration of gas flow to drilling-phase levels anticipated following cementing operations
  3. Ongoing assessment of helium and methane concentrations across both wells
  4. PR016 Production Right Application remains under PASA assessment

The Nooitgedacht drilling result, while requiring remedial follow-up, adds technical validation to D3 Energy’s broader Free State exploration programme across what is anticipated to be a meaningful appraisal and development pipeline.

Permit Location Status Key Feature Notes
ER315 Free State, SA Active — Production Right Application (PR016) lodged Up to 8% helium independently verified Flagship permit
PR016 Free State, SA Under PASA assessment Covers 15% of ER315; approx. 9% of total exploration right acreage Subject to Production Right Application
ER386 Free State, SA Exploration Right Application Contiguous with ER315; Virginia Fault corridor Hosts certified reserves and contingent resources
ER391 / ER392 / ER393 Free State, SA Exploration Right Applications Broader appraisal pipeline
TCP273 Free State, SA Technical Cooperation Permit Part of 479,409-acre land position

Get ASX Oil and Gas News Before the Market Moves

Big News Blast delivers FREE breaking ASX energy sector alerts directly to your inbox within minutes of release, complete with in-depth analysis. Join 30,000+ subscribers already staying ahead of the market. Click the “Free Alerts” button at Discovery Alert to start receiving alerts the moment news breaks.


Frequently Asked Questions

What did D3 Energy find at the Nooitgedacht drilling project?

D3 Energy confirmed gas-bearing zones in both the NGT245 D and NGT245 E wells at Nooitgedacht, with downhole camera footage capturing gas bubbling through the water column in NGT245 E before water from a deeper zone suppressed gas flow.

What is remedial cementing and why is D3 Energy using it?

Remedial cementing is a standard oil and gas technique used to seal off unwanted fluid zones within a wellbore — in this case, D3 Energy plans to isolate a deeper water production zone that has risen above the gas-bearing intervals and inhibited gas flow to surface.

Why did gas flow stop at the Nooitgedacht wells?

Geophysical logging identified a deeper water production zone in both wells where water has risen above the gas-bearing zones; combined with extremely low reservoir pressure, this water incursion was sufficient to suppress gas flow during completion operations.

How does the Nooitgedacht result fit into D3 Energy's broader South African portfolio?

Nooitgedacht sits approximately 40km from D3 Energy's Production Right application area and adds a new data point to the company's 479,409-acre land position across the Free State Province, which includes the flagship ER315 permit with independently verified helium concentrations of up to 8%.

What is the status of D3 Energy's Production Right Application in South Africa?

D3 Energy's PR016 Production Right Application, which covers 15% of the ER315 permit and approximately 9% of the company's total exploration right acreage, remains under assessment by South Africa's Petroleum Agency SA (PASA).

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.