Viridis Mining Secures US$154M Equity Funding for Colossus Rare Earth Project
Viridis Mining and Minerals (ASX: VMM) has completed the Viridis Mining Colossus rare earth project definitive feasibility study in Brazil, confirming what the company describes as a technically robust and commercially advanced development pathway. The study, led by engineering firm Hatch, sets out project economics, a cost structure positioned at the lower end of the global industry cost curve, and a schedule targeting a Final Investment Decision by late 2026.
For investors tracking the rare earth sector, the announcement is notable given Colossus is positioned as one of a limited number of near-term sources of non-Chinese rare earth supply to Western markets. The project's revenue is anchored by neodymium-praseodymium (NdPr), dysprosium (Dy) and terbium (Tb), the key inputs for permanent magnets used in electric vehicles and wind turbines.
According to the DFS, the project's financials hold up under two distinct pricing scenarios: current Chinese spot prices and a more conservative Western floor price framework. This dual-scenario approach is intended to demonstrate that the investment case is not dependent on a single pricing environment.
| Metric | Current Spot Case (US$129/kg NdPr) | Western Floor Price (US$110/kg NdPr) |
|---|---|---|
| Pre-Tax NPV8 | US$1,866M | US$1,856M |
| After-Tax NPV8 | US$1,196M | US$1,190M |
| Pre-Tax IRR | 47.0% | 46.9% |
| After-Tax IRR | 36.4% | 36.3% |
| Total Revenue (25yr) | US$8,540M | US$8,512M |
| Annual Operating Cashflow | US$168M | US$167M |
| Payback Period | 2.7 years | 2.7 years |
| CAPEX to First Production | US$405M (excl. contingency) | – |
| CAPEX (incl. contingency) | US$449M | – |
The company states the near-identical outcomes across both scenarios reflect the strength of Colossus' diversified rare earth basket. When NdPr prices are lower under the Western floor scenario, higher Dy and Tb prices largely compensate, which the DFS presents as evidence of basket resilience.
Understanding the underlying geology helps explain the project's reported cost advantages. Ionic adsorption clay (IAC) mineralisation forms through prolonged tropical weathering of alkaline bedrock. Rainwater releases rare earth elements from parent rocks, and these migrate downward through the soil profile, becoming weakly attached, or "adsorbed", onto the surfaces of clay minerals, predominantly kaolinite.
The processing implications are significant for investors. Because the rare earth ions are loosely bound to clay particles rather than locked inside hard rock, they can reportedly be released using a low-energy leach solution — in Colossus' case, a 0.3M ammonium sulphate solution at ambient temperature. This avoids the high-temperature roasting, acid baking, or energy-intensive crushing and grinding typically required for hard-rock deposits.
According to the company, the resulting advantages include:
Furthermore, Viridis states that Colossus hosts the highest-grade Magnetic Rare Earth Oxide (MREO) Measured and Indicated IAC resource reported globally, meaning the ore is comparatively enriched in higher-value rare earths rather than diluted with lower-value lanthanum and cerium.
| Term | Definition |
|---|---|
| TREO | Total Rare Earth Oxides, the full suite of rare earth oxide content |
| MREO | Magnetic Rare Earth Oxides, comprising Nd₂O₃, Pr₆O₁₁, Dy₂O₃ and Tb₄O₇ |
| MREC | Mixed Rare Earth Carbonate, the saleable intermediate product |
| NdPr | Neodymium-Praseodymium, the primary driver of magnet rare earth demand |
| C1 Cost | Direct cash operating cost per unit of production |
| AISC | All-In Sustaining Cost, comprising C1 cost plus royalties and sustaining/expansion capital |
| NPV8 | Net Present Value discounted at 8%, a standard project value measure |
| IRR | Internal Rate of Return |
| AACE Class 3 | Engineering cost estimate standard with ±15% accuracy, the benchmark for a DFS |
| IAC | Ionic Adsorption Clay, the mineralisation style hosting Colossus |
| EPCM | Engineering, Procurement and Construction Management delivery model |
| FID | Final Investment Decision |
According to independent market specialist Project Blue, Colossus is positioned at the lowest end of the first quartile of the global rare earth industry cost curve on a total REO basis.
| Cost Metric | Colossus DFS Estimate |
|---|---|
| C1 Operating Cost (Total REO, crude MREC basis) | US$9.84/kg REO |
| C1 Operating Cost (NdPr basis, net of DyTb credits) | US$15.30/kg NdPr |
| AISC (NdPr basis, net of DyTb credits) | US$26.70/kg NdPr |
| NdPr spot price (23 July 2026) | US$129/kg |
| Implied margin at spot (C1 basis) | ~US$114/kg NdPr |
The company attributes this cost position to several factors:
The C1 estimate was supported by a third-party energy broker for power pricing, independent logistics studies, regional labour benchmarking and specialist reagent market assessments, according to the DFS.
The DFS incorporates a refining circuit that selectively removes lower-value lanthanum from the crude MREC stream — an enhancement relative to the earlier Pre-Feasibility Study (PFS).
The upgraded product is reported to contain approximately 63.9% NdPr oxides and 2.8% DyTb oxides, compared with 37.4% NdPr and 1.5% DyTb under the PFS. Viridis states this concentrated product should consequently command stronger payability and reduced transport costs per payable unit.
The refining strategy draws on Solvay's rare earth separation expertise under a Letter of Intent signed in June 2026. Solvay has operated in Brazil for more than 100 years through its Paulínia manufacturing complex, and has agreed key commercial and technical principles for a broader partnership with Viridis. MREC samples produced at the Colossus Demonstration Plant have been shipped to Solvay's La Rochelle facility in France for product qualification.
A notable feature of the Viridis Mining Colossus rare earth project definitive feasibility study is that the process flowsheet has been tested at what the company describes as the largest known semi-industrial, continuous rare earth operation outside China, using representative Colossus ore.
During stabilised continuous operation from 6 to 31 July 2026, the Demonstration Plant reportedly achieved:
"The completion of the Colossus DFS is a defining milestone for Viridis. It confirms not only the industry-leading economics and resilience of Colossus, but importantly the significant maturity the Project has achieved across engineering, metallurgy, commercial arrangements and execution," said Rafael Moreno, Managing Director. "Our Demonstration Plant is outperforming the recoveries assumptions underpinning the DFS, the majority of the first five years is supported by Proved Ore Reserves, key offtake commercial terms have been finalised, Goldman Sachs is leading an advanced financing process, and we are positioned to award the EPCM contract and place orders for critical long-lead equipment."
Despite these outperforming results, the DFS economic model conservatively retains the metallurgical recovery assumptions derived from testwork by the Australian Nuclear Science and Technology Organisation (ANSTO), meaning the Demonstration Plant performance represents unbooked upside to the reported economics.
The DFS Ore Reserve is intended to provide the geological foundation for project financing discussions.
| Area | Classification | Tonnes (Mt) | TREO (ppm) | MREO (ppm) |
|---|---|---|---|---|
| Northern Concessions | Proved | 27.4 | 2,867 | 762 |
| Northern Concessions | Probable | 59.1 | 2,457 | 596 |
| Southern Complex | Probable | 113.6 | 3,129 | 766 |
| Total | Proved + Probable | 200.1 | 2,894 | 715 |
Key points from the Ore Reserve statement include:
TREO grade increased by 9.7% between the PFS and DFS reserve estimates, lifting contained TREO from approximately 530kt to 579kt whilst total reserve tonnage remained broadly unchanged.
Completion of the DFS is described by the company as the pivotal technical milestone enabling the debt financing process to progress toward credit approvals and term sheets.
| Institution | Status |
|---|---|
| Export Finance Australia (EFA) | Letter of Support for up to US$50M |
| Export Development Canada (EDC) | Letter of Interest for up to US$100M |
| Bpifrance | Letter of Support linked to a French offtake component |
| BNDES / FINEP (Brazil) | Selected for a Joint Support Plan under Brazil's strategic minerals funding initiative |
The DFS estimates the project could generate approximately US$3.83 billion of cash flow available for debt service over the 25-year Production Target, averaging approximately US$153M per annum against initial development capital of US$449M. The average EBITDA margin is projected at approximately 70%.
Viridis states it has advanced engineering, procurement and contractor engagement in parallel with the DFS to reduce the time between FID and construction start.
EPCM contract: A preferred contractor has been identified through an international tender process, with final negotiations under way. A Limited Notice to Proceed is targeted for late August 2026, with mobilisation planned for 1 September 2026.
Long-lead equipment: Five critical long-lead packages have progressed through competitive tendering and vendor metallurgical testwork using Colossus ore. Purchase orders are expected to be placed in Q3 2026.
Grid connection: The 138 kV high-voltage power connection contract has been awarded to DME, with 27MW of capacity secured and energisation targeted for December 2027.
Environmental licensing: The Preliminary Licence was granted in December 2025, and the Installation Licence application was submitted in May 2026. The Certificate of Regularity for Land Use and Occupation from the Municipality of Poços de Caldas has been received.
First production is targeted for 2H 2028, with steady-state production targeted for October 2028.
| Milestone | Target |
|---|---|
| EPCM contractor mobilisation | September 2026 |
| Senior debt term sheets / credit approvals | End September 2026 |
| Long-lead equipment purchase orders | Q3 2026 |
| Binding offtake agreement (Solvay) | Q3 2026 |
| Financial close | Q4 2026 |
| Installation Licence grant | 2026/2027 |
| Grid energisation | December 2027 |
| First production | 2H 2028 |
| Steady-state production | October 2028 |
Viridis has identified several factors it says could add value beyond the reported economics underpinning the Viridis Mining Colossus rare earth project definitive feasibility study in Brazil:
In conclusion, the company has indicated its near-term focus will be on finalising binding offtake arrangements, progressing the senior debt financing process, mobilising the EPCM contractor, and advancing the Installation Licence application toward approval, as it works toward a targeted Final Investment Decision.
The Viridis Mining Colossus DFS outlines a compelling investment case — from a first-quartile cost position and a US$1.19 billion after-tax NPV8, to Goldman Sachs-led financing and a clear pathway to first production in 2H 2028. For investors seeking to understand the full scope of the project's financials, ore reserve, execution strategy, and commercial arrangements, the complete DFS announcement is available now. Click here to access the full ASX announcement and explore what Viridis Mining (ASX: VMM) is building at Colossus.