ADX Energy Posts 3.15 MMCFPD Water-Free Gas Flow From Four Zones at HOCH-1
ADX Energy Ltd (ASX: ADX) has reported a positive production testing result from the Hochfeld-1 (HOCH-1) shallow gas exploration well in Upper Austria. The ADX Energy HOCH-1 gas flow results in Upper Austria represent a notable early milestone, with the first gas sand interval perforated delivering a clean-up flow rate of 2.8 million cubic feet per day (equivalent to 467 boepd) on a 16/64 inch choke, with flowing wellhead pressure of 940 psi and rising.
According to the ASX release on 18 June 2026, this initial result is an early indicator for a broader, multi-zone testing and appraisal campaign within the ADX-AT-I exploration licence, where ADX Energy Ltd is operator and holds a 50% economic interest in the HOCH prospect.
HOCH-1 key test result (Zone 1):
| Parameter | Result |
|---|---|
| Average gas flow rate | 2.8 MMcf/d (~467 boepd equivalent) |
| Choke size | 16/64 inch (small) |
| Flowing wellhead pressure | 940 psi and rising |
| Perforated interval depth | 1,464.6 – 1,466.6 m (Zone 1) |
| Water production | None detected |
According to ADX Energy Ltd, the water-free gas flow and increasing wellhead pressure from Zone 1 indicate good inflow performance from the tested sand.
"The water free flow rate and flowing pressure is very encouraging indicating good inflow performance for the sand interval."
– ADX Energy Ltd, ASX release, 18 June 2026
The HOCH-1 shallow gas exploration well was drilled, cased and completed on 15 May 2026 within the ADX-AT-I exploration licence in Upper Austria. It is the first of three shallow gas prospects planned for drilling in the area, with two additional gas prospects already permitted for drilling in 2026.
Zone 1, the first interval selected for testing, is a Basin Floor Fan (BFF) reservoir perforated at approximately 1,465 metres. The testing to date represents a clean-up flow, meaning the well is in the early stages of production testing and is still clearing residual drilling and completion fluids.
The following technical points are highlighted in the ASX announcement:
From an investor perspective, several aspects are of interest:
Production testing at HOCH-1 is being conducted in two phases, according to ADX Energy Ltd:
Following the initial clean-up of Zone 1, the planned next steps reported by the company are:
This process is a standard methodology in gas well appraisal. Furthermore, the stable flow period provides information on how the well behaves under controlled production, whilst the pressure build-up during shut-in helps estimate how far the reservoir extends, how well connected the gas-containing rock is, and how much gas could potentially be recoverable from the tested interval.
ADX has also outlined that the remaining sand intervals will be perforated sequentially, each followed by brief clean-up flows. The perforation sequence and flow periods will be adjusted based on the inflow performance of each zone, meaning that test design will be refined as more data is collected.
A Basin Floor Fan is a type of sedimentary deposit formed when sand and other material move down a slope and spread out across the bottom of a sedimentary basin. Over time, these deposits are buried and turned into rock.
In the subsurface, BFF deposits:
HOCH-1 Zone 1 is described by ADX Energy Ltd as a BFF reservoir that is expected to be deposited over an extensive area.
For investors following the ADX Energy HOCH-1 gas flow results in Upper Austria, the BFF classification is particularly relevant for several reasons:
However, the actual recoverable volumes will depend on measured pressure behaviour, gas properties, and further zone testing. Consequently, the planned pressure build-up analysis at HOCH-1 is a central data point for refining estimates.
To understand the HOCH-1 update from ADX Energy Ltd, it is useful to clarify some of the main technical terms and processes referenced in the ASX announcement.
| Term | Accessible explanation |
|---|---|
| MMcf/d | Million cubic feet per day – a common unit to measure gas flow. |
| boepd | Barrels of oil equivalent per day – gas volumes converted into an oil-equivalent rate for comparison. |
| Choke | A device at the wellhead that controls how much gas can flow to the surface. |
| Wellhead pressure | The pressure measured at the surface of the well while it is flowing. |
| Pressure build-up | The pressure rise recorded after the well is shut in, used to estimate reservoir size and connectivity. |
| BFF (Basin Floor Fan) | A broad, fan-shaped sand deposit formed at the base of a basin that can store hydrocarbons. |
| Hall and Base Hall formations | Specific rock layers in the Upper Austria licence that host the gas reservoirs targeted by HOCH-1. |
For investors, understanding these concepts helps interpret what early test results such as those from HOCH-1 may signal about potential future production and reserves.
According to ADX Energy Ltd, HOCH-1 is part of a broader shallow gas exploration programme in Upper Austria. Key facts from the ASX release include the following:
The testing strategy has been set up in a structured way. Phase 1 focuses on the upper Hall formation, covering up to three firm gas zones and a fourth contingent zone subject to results. Phase 2, in turn, focuses on the lower Base Hall formation.
The company has indicated that sand intervals will be perforated one after another, with each zone receiving a brief clean-up flow. The order of perforation and duration of flow for each zone will be determined by the inflow performance observed, allowing ADX Energy Ltd to prioritise zones that demonstrate better deliverability and build up a clearer picture of the overall gas potential of the HOCH-1 well.
HOCH-1 and programme snapshot
| Item | Detail |
|---|---|
| Well name | Hochfeld-1 (HOCH-1) |
| Licence | ADX-AT-I, Upper Austria |
| Operator | ADX Energy Ltd |
| ADX economic interest | 50% |
| Wells in 2026 shallow gas programme | 3 shallow gas prospects (HOCH-1 first) |
| Gas reservoirs encountered at HOCH-1 | Up to 8 (Hall and Base Hall formations) |
| Testing phases | 2 (Hall then Base Hall) |
| Zones in Phase 1 | Up to 3 firm + 1 contingent |
While the HOCH-1 programme remains at an appraisal stage, the ASX release from ADX Energy Ltd highlights several points that may be relevant to investors assessing the company.
The 2.8 MMcf/d (467 boepd equivalent) clean-up flow on a small 16/64 inch choke indicates that Zone 1 has the capacity to deliver gas at rates that may be commercially meaningful, subject to costs, infrastructure and market conditions.
As the well has not yet undergone a sustained, optimised flow period, there is still uncertainty around long-term deliverability, which the planned 14-hour stable flow and pressure build-up analysis are designed to address.
The company reports a water-free flow from Zone 1 during the clean-up. For gas wells, persistent early water production can sometimes indicate proximity to a water contact or potential for water encroachment under production.
In contrast, gas without water at this stage can suggest a cleaner gas reservoir interval, although longer-term behaviour still needs to be monitored through extended testing and, if applicable, production.
With up to eight gas reservoirs identified in HOCH-1, and two additional shallow gas prospects permitted for drilling in 2026, the programme outlined by ADX Energy Ltd provides several upcoming technical catalysts:
Each step may refine the understanding of gas potential within the ADX-AT-I licence.
The description of Zone 1 as a BFF reservoir deposited over an extensive area suggests that, if pressure data indicates good connectivity and reservoir quality, the volume of connected gas associated with this interval could be material. However, this remains dependent on results of pressure build-up analysis, testing of additional zones, and further drilling within the same geological setting.
According to the ASX announcement, the following operational steps at HOCH-1 are expected in the near term:
For investors following ADX Energy Ltd, each of these steps is likely to be reported through further ASX releases and may affect the technical and commercial interpretation of the HOCH-1 well.
The ADX Energy HOCH-1 gas flow results in Upper Austria present ADX Energy Ltd as an active operator in a European onshore gas exploration setting. In summary, the key highlights include:
With oversight of technical information by a qualified geophysicist with 30 years of experience, as stated in the ASX announcement, the data and interpretations presented by ADX Energy Ltd will be further refined as testing progresses.
For investors monitoring small-cap energy companies with active drilling and near-term operational updates, the ADX Energy HOCH-1 gas flow results in Upper Austria represent a developing story that may warrant ongoing attention as further testing milestones are reached.
ADX Energy Ltd (ASX: ADX) is actively testing up to eight gas reservoirs at HOCH-1 in Upper Austria, with two additional shallow gas prospects already permitted for drilling in 2026. With Zone 1 delivering encouraging early clean-up flow rates and a structured multi-zone testing programme underway, there are several near-term operational milestones that investors may wish to track closely. To learn more about ADX Energy's projects, exploration licence, and investment case, visit the company's official website at adx-energy.com.