KGL Resources Awards Processing Plant Contract Ahead of Imminent FID at Jervois Copper

KGL Resources has awarded Sedgman a full design, procurement and construction contract for the Jervois Copper Project processing plant — with Final Investment Decision now planned within weeks and procurement of long-lead equipment already underway.
By William Hadrian -
  • KGL Resources has awarded Sedgman the DPC contract for the Jervois Copper Project processing plant, with Final Investment Decision and project execution both planned for the coming weeks.
  • Sedgman has been involved with the Jervois asset since 2017, covering testwork, feasibility studies, front-end engineering and procurement — this is a long-standing technical partnership converting into full delivery, not a new contractor relationship.
  • The processing plant is designed for 2.0 million tonnes per annum throughput, targeting approximately 30,000 tonnes of copper per annum at steady state over an initial 10-year mine life.
  • The contract scope was expanded to allow more cost-effective early installation of future plant additions, with terms remaining in line with the Baseline Economic Model on both capital cost and schedule.
  • A funded exploration programme running alongside project development has already generated a major copper discovery at Jervois, adding a resource growth dimension beyond the defined mine life.
Summarise with AI:

Jervois copper project moves into execution as KGL awards processing plant contract

KGL Resources (ASX: KGL) has awarded Sedgman, a member of the CIMIC Group, the design, procurement and construction (DPC) contract for the processing plant at its 100%-owned Jervois Copper Project in the Northern Territory. The award represents an important milestone toward Final Investment Decision (FID) and project execution, both planned for the coming weeks.

Jervois is a high-grade copper project with funding already secured through to production. The processing plant is designed for 2.0 million tonnes per annum (Mtpa) throughput, producing a single copper concentrate using conventional crushing, grinding, flotation and thickening.

Jervois Copper Project Key Metrics Dashboard

What Sedgman will deliver

Under the contract, Sedgman will be responsible for the full integrated delivery of the Jervois processing plant. Procurement of critical long-lead process equipment and detailed engineering is already underway, signalling genuine execution momentum ahead of FID.

The contract scope covers:

  • Detailed design and engineering
  • Procurement of equipment and materials
  • Construction of the processing plant
  • Commissioning and testing
  • Associated infrastructure and services

One notable development is that the contract scope has been increased to allow for more cost-effective early installation of future plant additions. Importantly, the terms remain in line with the assumptions made in the Baseline Economic Model in relation to capital cost and schedule, meaning the expansion does not introduce cost or timeline risk for investors.

Project Feature Detail
Plant throughput 2.0Mtpa
Processing method Crushing, grinding, flotation, thickening
Product Single copper concentrate
Steady-state output ~30,000tpa copper
Mine life 10 years (initial)

What a design, procurement and construction contract means for investors

A DPC contract is an agreement under which a single contractor takes responsibility for designing, procuring all equipment and materials, and physically building the facility. For mining projects, this integrated structure matters because it concentrates accountability in one party rather than splitting it across multiple separate contractors who may not coordinate effectively.

Awarding the full DPC scope to one contractor reduces the coordination risk that often leads to cost blowouts and schedule delays on complex construction projects. When design, procurement and construction are managed by separate parties, gaps between them can create expensive problems. A single integrated contractor removes that gap.

In Jervois’ case, the execution risk is further reduced by Sedgman’s history with the asset. Sedgman has been involved with the project since 2017, working through historical testwork review, metallurgical testwork, pre-feasibility and feasibility studies, value engineering, front-end engineering design and procurement activities. This is not a new relationship being established under pressure ahead of construction; it is a long-standing technical partnership being converted into full delivery.

Sedgman’s parent, CIMIC Group, is one of Australia’s largest construction and services groups, adding institutional depth behind the contract. The combination of established asset knowledge and a well-resourced contractor parent positions the Sedgman team with clear design maturity and implementation planning already embedded heading into execution.

What comes next for Jervois and KGL shareholders

With the DPC contract now awarded, the forward path is FID and project execution, both planned for the coming weeks, followed by construction and commissioning phases.

KGL CEO Sam Strohmayr

“Advancing the Jervois Copper Project into design, engineering and construction is a critical step in progressing the project towards operations. Sedgman’s deep technical knowledge of the asset and processing requirements, substantial experience in project delivery, and continuity from earlier study phases position the Sedgman team well to partner with the KGL owners’ team in the development of the Jervois Copper Project.

“Both teams have worked collaboratively throughout the development and negotiation of the contract. KGL looks forward to continuing this partnership approach through the construction and commissioning phases of the Project.”

Sedgman Managing Director Grant Fraser

“We’re pleased to continue our long-standing relationship with KGL Resources as the Jervois Copper Project moves into delivery. Having supported the project from its early study stages, our team brings deep knowledge of the processing requirements and a clear understanding of the design intent. This contract award reflects Sedgman’s ability to integrate design, procurement, construction, commissioning and testing to support the project through execution.”

At steady state, the Jervois project is expected to produce approximately 30,000 tonnes of copper per annum, with an initial mine life of 10 years and significant silver and gold by-products. Alongside the project’s development, KGL is also running a funded exploration programme targeting resource growth, mine-life extension and new discoveries across the broader Jervois and Unca Creek tenements.

The exploration programme has already generated results worth tracking: a major copper discovery at Jervois has confirmed new mineralisation along previously underexplored corridors within the tenement package, adding a resource growth dimension to the project beyond its defined mine life.

With the DPC contract in place, procurement underway, and FID planned for the coming weeks, KGL is progressing along the trajectory it has outlined toward production.

Don’t Miss the Next ASX Copper Breakout

Get FREE breaking ASX copper news delivered to your inbox within minutes of release, complete with in-depth analysis. Join 30,000+ subscribers already staying ahead of the market. Click the “Free Alerts” button at Discovery Alert to receive the moment market-moving copper and mining news breaks.


Frequently Asked Questions

What is a design, procurement and construction contract in mining?

A DPC contract places a single contractor in charge of designing the facility, procuring all equipment and materials, and physically building it — concentrating accountability in one party and reducing the coordination gaps between separate contractors that often cause cost overruns and schedule delays.

What will the Jervois Copper Project produce at steady state?

At steady state, the Jervois processing plant is designed to produce approximately 30,000 tonnes of copper per annum from 2.0 million tonnes of ore throughput per year, with silver and gold by-products, over an initial mine life of 10 years.

Why did KGL Resources choose Sedgman for the Jervois processing plant contract?

Sedgman has been involved with the Jervois project since 2017, working through metallurgical testwork, feasibility studies, front-end engineering and procurement — giving the contractor deep asset knowledge and design continuity that reduces execution risk heading into construction.

When is KGL Resources expected to make its Final Investment Decision on Jervois?

KGL Resources has indicated that Final Investment Decision and project execution are both planned for the coming weeks following the DPC contract award to Sedgman.

What does the Jervois exploration programme mean for the project's mine life?

KGL is running a funded exploration programme targeting resource growth and mine-life extension across the Jervois and Unca Creek tenements, and has already confirmed a major new copper discovery along previously underexplored corridors — providing a potential pathway to extend the initial 10-year mine life.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.

About the Publisher