Reach Resources Moves Into Step-Out Drilling Targeting Untested SE Gold Workings

Reach Resources (ASX: RR1) has completed 163 RC holes across 4,238m of grade control drilling at Murchison South and immediately launched a 24-hole step-out programme targeting untested historical gold workings — with assay results from both programmes due by late November 2026.
By William Hadrian -
  • Reach Resources completed 163 RC holes for approximately 4,238m on a tight 10m x 10m grid at the NW Pit, with grade control assay results expected in early October 2026.
  • A 24-hole, ~2,000m step-out expansion programme commenced immediately after grade control wrapped, targeting Primrose Shear extensions and a south-east zone of historical gold workings that has never previously been drill tested.
  • The south-east old workings target sits outside the current Mineral Resource Estimate boundary, meaning positive results could directly expand the project's resource footprint.
  • Mine planning and scheduling work is being progressed by SMS Mining Pty Ltd, a subsidiary of Andel Resources, with the Kirkalocka Process Plant identified as a potential processing pathway if the resource grows.
  • Step-out assay results are expected in late November 2026, representing the most significant near-term catalyst for potential MRE growth at Murchison South.
Summarise with AI:

Grade control complete, step-out drilling now underway at Murchison South

Reach Resources (ASX: RR1) has completed its grade control (GC) drill programme at the proposed NW Pit within the Murchison South Gold Project near Payne’s Find, Western Australia, and moved immediately into a step-out expansion programme. There was no pause between phases, with the step-out commencing as the GC programme wrapped in early September, reflecting the ongoing momentum under the company’s partnership with Andel Resources.

The GC programme delivered 163 reverse circulation (RC) holes drilled for approximately 4,238m on a tight 10m x 10m grid pattern. The original planned total of 5,200m was not reached due to old workings in the area making it unsafe to drill in certain locations, though the company confirmed this did not impact the programme’s objectives — sufficient holes were completed to cover affected areas. Samples have been dispatched to the laboratory, with assay results expected to be reported to the market in early October.

The step-out expansion programme now underway comprises approximately 24 RC holes for a total of ~2,000m, with drilling targeted for completion by early October and assay results expected in late November.

Murchison South Drill Programme Comparison

What the step-out programme is targeting

The step-out programme has two distinct targets, each with different geological significance:

Target 1 — Primrose Shear extensions:

  • Up and down strike extensions of the Primrose Shear beyond the currently proposed pits
  • The Primrose Shear is described by the company as the “major gold feeder structure” at Murchison South

The current step-out programme builds on a series of earlier findings, with gold opportunities at Murchison South having come into sharper focus through preceding work that helped define the Primrose Shear as the project’s primary structural host.

Target 2 — South-east old gold workings:

  • A dense concentration of historical gold workings located to the south-east of the proposed pits
  • This area has not previously been drill tested, making it a genuinely untested target explicitly identified as such in the announcement
  • Located outside the current Mineral Resource Estimate (MRE) boundary

It is important to note that the pit shells referenced in Figure 1 of the announcement are conceptual only. They are derived from Andel’s internal mine pit optimisation process, are not based on a scoping, pre-feasibility, or feasibility study, and do not constitute a production target for the purposes of the ASX Listing Rules.

Jeremy Bower, CEO

“With grade control drilling now complete at the NW Pit, we have moved straight into a step out program designed to test the extensions of the Primrose Shear and in particular test a concentrated area of old gold workings which lie outside of the current MRE and to the south-east of our current proposed pits…”

Understanding grade control drilling and why it matters for mine planning

Grade control drilling is not exploration drilling. Where exploration drilling aims to discover mineralisation and establish a resource estimate across a broad area, GC drilling operates at a much tighter scale, mapping the precise distribution of gold grades across planned mining benches.

The 10m x 10m grid spacing used at the NW Pit is significantly tighter than typical exploration programmes. That density is deliberate — it provides the high-resolution data needed to schedule which blocks of ore get mined, in what order, and at what grade, rather than working from broader resource estimates alone.

At Murchison South, the GC data feeds directly into mine planning and scheduling work being progressed by SMS Mining Pty Ltd, a subsidiary of Andel Resources. Completing this programme moves the project meaningfully closer to production readiness. The company’s existing agreement with Andel also references the Kirkalocka Process Plant as a potential processing pathway for Murchison South mineralisation if the resource grows.

Key milestones and what investors should watch

The upcoming catalyst schedule for Murchison South is clearly defined, with three distinct events across the coming months.

Milestone Programme Expected Timing Significance
GC assay results reported NW Pit Grade Control Early October 2026 Informs mine planning at NW Pit
Step-out drilling completed Primrose Shear / SE workings Early October 2026 Tests resource footprint extensions
Step-out assay results Step-out expansion programme Late November 2026 Potential MRE growth signal

Assay results from both programmes are pending, and their outcomes remain unknown at this stage. Beyond Murchison South, Reach Resources holds a strategic shareholding in ASX-listed Delta Lithium (ASX: DLI), providing exposure to Delta Lithium’s portfolio of Australian lithium projects, and an investment in REEcycle Inc., a company that has developed a patented technology for recycling rare earth elements from permanent magnets used in electric vehicles, wind turbines, and other applications.

Don’t Miss the Next ASX Gold Discovery

Get breaking ASX gold news delivered to your inbox within minutes of release, complete with in-depth analysis, all for FREE. Join 30,000+ subscribers already staying ahead of the market. Click the “Free Alerts” button at Discovery Alert to make sure the next major gold announcement lands in your inbox the moment it breaks.


Frequently Asked Questions

What is grade control drilling and why does it matter for Murchison South?

Grade control drilling maps the precise distribution of gold grades across planned mining benches at a very tight spacing — in this case 10m x 10m — providing the high-resolution data needed to schedule which ore blocks get mined, in what order, and at what grade. Completing this programme at the NW Pit moves Murchison South meaningfully closer to production readiness.

What is the Primrose Shear at Murchison South?

The Primrose Shear is described by Reach Resources as the major gold feeder structure at the Murchison South Gold Project, and the step-out programme is targeting up and down strike extensions of this structure beyond the currently proposed pits.

When will Reach Resources report assay results from the Murchison South drilling programmes?

Grade control assay results from the NW Pit programme are expected in early October 2026, while assay results from the 24-hole step-out expansion programme are expected in late November 2026.

What is the south-east old gold workings target and why is it significant?

The south-east target is a dense concentration of historical gold workings located outside the current Mineral Resource Estimate boundary that has never previously been drill tested. Positive results from the step-out programme targeting this area could directly expand Murchison South's resource footprint.

What other assets does Reach Resources hold beyond Murchison South?

Beyond Murchison South, Reach Resources holds a strategic shareholding in ASX-listed Delta Lithium (ASX: DLI), providing exposure to Australian lithium projects, and an investment in REEcycle Inc., which has developed patented technology for recycling rare earth elements from electric vehicle and wind turbine permanent magnets.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article

Breaking ASX Alerts Direct to Your Inbox

Join +30,000 subscribers receiving alerts.
Join thousands of investors who rely on Discovery Alert for timely, accurate mining and commodities market intelligence.