GR Engineering Locks in $50M EPC Deal for Cosmic Boy Refurbishment

Medallion Metals has executed a $50 million lump sum GR Engineering Cosmic Boy EPC contract — landing within $1 million of the Feasibility Study estimate — with processing targeted to commence in October 2026 and first mine production at Kundip set for Q2 2027.
By William Hadrian -
  • Medallion Metals has executed a $50 million lump sum EPC contract with GR Engineering Services for the Cosmic Boy Concentrator refurbishment — within $1 million of the $49 million Feasibility Study estimate.
  • The lump sum structure transfers cost overrun risk to GR Engineering Services, providing Medallion shareholders with fixed-cost certainty through to commissioning.
  • Concrete pouring is expected to begin the first week of September 2026, with processing commencement on third-party ore targeted for early October 2026.
  • GR Engineering Services originally designed and built the Cosmic Boy Concentrator in 2009, reducing execution risk through direct institutional knowledge of the plant and Ravensthorpe mineralogy.
  • First production at Kundip is targeted for Q2 2027, with the Early Processing Strategy on third-party ore providing operational activity at CBC ahead of mine production coming online.
Summarise with AI:

$50 million EPC contract locks in Cosmic Boy construction with GR Engineering

Medallion Metals (ASX:MM8) has executed a $50 million lump sum Engineering, Procurement and Construction (EPC) contract with GR Engineering Services (ASX:GNG) for the refurbishment and conversion of the Cosmic Boy Concentrator (CBC). The contract covers design, procurement, construction and commissioning to convert CBC into a standalone facility capable of producing copper concentrate and gold doré. It replaces the earlier $7.6 million Early Works Agreement (EWA) that commenced in June 2026, with processing operations expected to begin in October 2026, initially on third-party ore.

Contract details and what the $50 million covers

The EPC contract was executed by Medallion’s wholly owned subsidiary, Myamba Minerals Pty Ltd. The scope covers the remaining engineering, procurement, construction and commissioning activities required to refurbish and modify CBC as a standalone processing facility, targeting the 650ktpa throughput rate established in the Feasibility Study.

The $50 million contract value compares favourably with the $49 million estimated in the Feasibility Study for establishing gold and copper processing capability at CBC — a signal of cost discipline that investors will note. GR Engineering Services (GRES) has been working under the EWA since June 2026, completing the front end engineering and design (FEED) programme and ordering long-lead items. That prior work means the project transitions directly into full EPC delivery without interruption.

Cosmic Boy EPC Contract Cost Comparison

Key contract specifics at a glance:

  • Contracting party: Myamba Minerals Pty Ltd (wholly owned subsidiary of Medallion Metals)
  • Contract type: Lump sum EPC
  • Contract value: $50 million
  • Throughput target: 650ktpa (per Feasibility Study)
  • Scope: Design, procurement, construction and commissioning of CBC refurbishment
  • Concrete pouring: Expected to commence first week of September 2026
  • Processing commencement: Targeted early October 2026

GRES originally designed and constructed the CBC in 2009, making the partnership a logical one given the contractor’s institutional knowledge of both the existing plant and Ravensthorpe mineralogy.

Paul Bennett, Managing Director, Medallion Metals

“We are very pleased to have finalised the EPC contract and to be partnering with GR Engineering on the refurbishment and modification of Cosmic Boy. Having originally designed and constructed the facility in 2009, GRES brings a detailed understanding of the existing plant as well as extensive knowledge of the Ravensthorpe mineralogy making this a logical partnership for Medallion and an extension of long-standing relationships between the two organisations. The contract value has been agreed in line with the Feasibility estimate and on terms that provide cost certainty. Its execution is another important operational step that brings us closer to production. Development works are now well underway at both Forrestania and Ravensthorpe. We expect to commence processing operations at Cosmic Boy in October, initially on third-party ore, while advancing mine development at Kundip with first production targeted in the second quarter of 2027.”

What is an EPC contract and why it matters for mining investors

An EPC contract (Engineering, Procurement and Construction) is an agreement where a single contractor takes full responsibility for delivering a project from design through to completion, under one fixed price. The contractor manages everything: the engineering drawings, sourcing of equipment and materials, physical construction, and commissioning. The mine owner knows upfront what it will cost.

This is meaningfully different from earlier-stage agreements like the EWA, which covered front end engineering and design, procurement of long-lead items, and site readiness activities. The EWA was a necessary precursor; the EPC contract is the main event.

In Medallion’s case, the $50 million lump sum aligns almost exactly with the $49 million Feasibility Study estimate, meaning there is no cost blowout signalled at this stage of the project.

Development momentum across both project sites

Forrestania Gold Project (FGP) — Cosmic Boy progress

Construction and pre-processing activities are advancing across multiple workstreams at the Cosmic Boy site:

  • Surface earthworks complete; civil works progressing
  • Second ball mill components in transit, scheduled to arrive at the Port of Fremantle 17 September 2026 before transport to site
  • Third-party ore being delivered and stockpiled on the CBC ROM pad
  • Fabrication of additional carbon-in-column tanks well advanced
  • Processing expected to commence early October 2026 (Early Processing Strategy)

Ravensthorpe Gold Project (RGP) — mine development advancing

At Ravensthorpe, site preparation activities are tracking toward the box cut excavation that will mark the start of mine development proper:

  • Civil works and infrastructure readiness progressing
  • Box cut excavation scheduled to commence September 2026
  • Accommodation rooms being relocated from Forrestania to Ravensthorpe camp
  • Mine offices and underground infrastructure relocating from Spotted Quoll to RGP
  • First production at Kundip targeted Q2 2027
Project Site Activity Status Expected Date
FGP Cosmic Boy Site earthworks Complete —
FGP Cosmic Boy Ball mill components arrival (Port of Fremantle) In transit 17 Sep 2026
FGP Cosmic Boy Processing commencement (third-party ore) Advancing Early Oct 2026
RGP Ravensthorpe Box cut excavation Scheduled Sep 2026
RGP Kundip First production Targeted Q2 2027

Investment thesis — cost certainty, construction momentum, near-term production

Three signals stand out from this announcement for investors assessing Medallion’s project trajectory. The $50 million contract value is in line with the Feasibility Study’s $49 million estimate, indicating no cost blowout at this stage of construction. Concrete pouring is expected to begin in the first week of September 2026, meaning execution risk is actively being reduced rather than deferred. And the timeline is specific: processing commencing October 2026 on third-party ore, with first production at Kundip targeted for Q2 2027.

The Early Processing Strategy on third-party ore is also worth noting. It represents a near-term pathway to earlier operational activity at the refurbished facility, predating Kundip production. With GRES already on site and earthworks complete, the project is well past the planning stage.

Don’t Miss the Next ASX Gold and Copper Development Milestone

Get FREE breaking ASX mining news delivered to your inbox within minutes of release, complete with in-depth analysis already done for you. Join 30,000+ subscribers who stay ahead of the market on gold, copper and beyond. Click the “Free Alerts” button at Discovery Alert to start receiving alerts the moment market-moving news breaks.


Frequently Asked Questions

What is an EPC contract in mining?

An EPC (Engineering, Procurement and Construction) contract is a fixed-price agreement where a single contractor takes full responsibility for designing, sourcing equipment, building, and commissioning a facility — giving the mine owner cost certainty from the outset.

What does the Medallion Metals Cosmic Boy EPC contract cover?

The $50 million lump sum EPC contract with GR Engineering Services covers the full refurbishment and conversion of the Cosmic Boy Concentrator into a standalone facility capable of producing copper concentrate and gold doré, targeting a throughput rate of 650ktpa.

When will Medallion Metals start processing ore at Cosmic Boy?

Medallion Metals is targeting processing commencement at the Cosmic Boy Concentrator in early October 2026, initially using third-party ore under its Early Processing Strategy, ahead of first mine production at Kundip which is targeted for Q2 2027.

Why did Medallion Metals choose GR Engineering Services for the Cosmic Boy contract?

GR Engineering Services originally designed and constructed the Cosmic Boy Concentrator in 2009, giving them detailed knowledge of the existing plant and Ravensthorpe mineralogy — making them the logical choice for the refurbishment and a continuation of a long-standing relationship with Medallion.

How does the $50 million EPC contract compare to the Feasibility Study estimate?

The $50 million lump sum EPC contract is within $1 million of the $49 million estimated in the Feasibility Study for establishing gold and copper processing capability at Cosmic Boy, indicating no cost blowout at this stage of the project.

William Hadrian
By William Hadrian
Partnerships Director
William supports Discovery Alert subscribers across Australia and overseas, helping them tailor alerts, troubleshoot technical issues, and optimise platform settings to suit their workflow.
Learn More
Companies Mentioned in Article